(pressing HOME will start a new search)
|
|
A
MECHANICAL ELECTRICAL CURRICULUM FOR CONSTRUCTORS
J.
Trost |
This
paper discusses student prepared drawings, and operating cost estimates;
two valuable components of an effective Mechanical/Electrical curriculum
for constructors. KEY WORDS:
Mechanical/electrical, design, drawing, operating cost, evaluating
alternatives. |
INTRODUCTION
Mechanical
Electrical (M/E) subsystems account for 20 to 25% of building construction cost
and a large part of building operating cost. It follows that a substantial
number of construction graduates may pursue careers constructing, operating, and
maintaining building M/E systems. Construction curricula typically dedicate 2 to
5% of their available hours to the M/E subject area; this paper begins with a
brief overview of course goals and then focuses on drawings and operating cost
estimates as valuable components of an effective M/C curriculum.
COURSE
GOAL AND OBJECTIVES
The
M/E curriculum goal is to provide a foundation of information and experience
that enables graduates to make informed value , judgements. Curriculum
objectives are outlined briefly below; these objectives are not proposed as
mandatory standards for a M/E curriculum. Rather, they are presented as a
starting point for discussion of two topics addressed in this paper.
Objectives
Students
successfully completing M/E course work should be able to:
|
The
following discussion emphasizes objectives 7 and 8; and proposed that these
objectives can be realized most effectively using student prepared drawings, and
student prepared operating cost projections.
DRAWINGS
Materials,
structure, M/E subsystems, and construction are interrelated elements of the
building process. Informed judgments and decisions before and during
construction should be based on a working knowledge of each individual element
and its relationship to all others. Evaluation of an alternative curtain wall
panel for example, should include U values, weight, sealing and wind bracing
comparisons as well as the usual initial cost and installation time
considerations.
Over
more years than I care to remember, I have concluded that students can best
begin to understand the interrelationships of building subsystems by sizing,
selecting, and detailing an element and its relationship with other building
elements. Preparation of a set of M/E drawings for a commercial building is a
curriculum approach that can help students understand the M/E topic area and its
impact on the building process.
Drawing
preparation is particularly effective because it requires selection and
detailing of a M/E installation based on previously completed student
calculations of heat loss and gain, electrical, lighting, and water
requirements. The drawings reinforce lecture discussions and confirm the
relationships between orientation, material selection, and M/E subsystems. In
addition preparing drawings, provides familiarity with available M/E contract
drawings
that are an essential part of all construction projects. Finally, drawings are
the practical route to understanding the space requirements necessaryy to
accommodate and integrate M/E subsystems with building structure, materials, and
construction.
I
believe construction students who have developed a set of M/E drawings are
better able to:
|
Unfortunately,
correcting and evaluating M/E drawings is not the easiest way for an instructor
to cover course material, but the potential student benefit from the drawing
effort can produce stronger graduates.
ESTIMATING OPERATING COST
A
second valuable component of an effective M/E curriculum is operating cost
analysis; it helps students understand the impact of design and material
decisions and is the basis for informed value judgments concerning construction
alternatives.
An
operating cost projection is the logical culmination of student efforts in M/E
design and equipment selection; it can focus student interest and develop a
sound basis for evaluation of M/E subsystems. Selecting the "best" M/E
system for a given building naturally involves cost as well as comfort
considerations; and the operating costs tie M/E subsystems into nearly all other
building subsystems. Materials, insulation, orientation, even structural
detailing, affect the operating costs incurred to maintain comfortable indoor
conditions.
Operating
costs for building lighting or water supply are easily estimated based on past
experience records from similar buildings. However, HVAC costs are a bit more
challenging because of three areas of uncertainty. Actual
infiltration-ventilation conditions, actual equipment efficiency, and actual
"full load" operating hours, are all factors that vary considerably
with building quality, building operation, and climate.
I
use equivalent full load hour maps as a starting point for estimating annual
HVAC operating costs; they are approximations based on limited experience,
weather maps, manufacturer's information, and a good deal of (hopefully)
inspired judgement. The following 7 pages from Efficient Buildings
heatinq and cooling summarize the process I use to estimate
operating costs and evaluate construction alternatives.
You
will notice the maps are very small and very general. While I am confident about
their application in specific areas where I have historical utility cost
records, I have not confirmed their applicability throughout the U.S. Should you
decide to apply them, confirm or adjust heating and cooling hours based on local
experience. The best source of "full load" operating hour data for
HVAC installations is your local electrical utility and heating fuel supplier.
They maintain extensive historical data that correlate electrical and fuel
consumption with weather conditions and building type.
After
improving on my general maps and adjusting my approximations concerning heat
contributed by people and lights, confirm your operating cost estimates by
checking several existing buildings where historical utility data is available.
Then pass your results on to students for improvement and application. Students
respond to an economic basis for evaluating construction alternatives and their
impact on operating costs with interest and enthusiasm.
The
following 7 pages from Efficient Buildings are reprinted by ASC
with permission.
5.0
Estimating Annual Energy Requirements
Calculated
values for heat loss and heat gain may be used to estimate annual energy
requirements and costs. The heating and cooling hours maps at right give
estimated full-load operating hours for heating and cooling equipment. Maps are
rough estimates; better values can be obtained from local utilities. Do not
apply map values to buildings that are heated and cooled occasionally, like
churches and dance halls, or to buildings operated 24 hours a day. To estimate
annual energy requirements in BTU/yr (BTU per year) multiply the peak heat loss
and gain values for a building by the annual full-load heating and cooling hours
shown on the maps.
Example:
House
Find
the total annual heating and cooling BTU for a house with a peak heat loss of
77,273 BTUH and a peak heat gain of 33,357 BTUH (p. 17 and 27) located at point
"H" on the maps.
|
|
|
Example:
Office
Find
the total annual heating and cooling BTU for an office building if the
calculated peak heat loss is 406,850 BTUH and peak heat gain is 630,162 BTUH (p.
19 and 29) located at point "0" on the maps.
|
1987
A-C Publications |
|
5.1
Estimating Annual Energy Costs
BTU/yr
can be converted to $/yr (dollars per year) if you know the cost of energy and
the efficiency of the heating/cooling equipment. The following calculations use
the preceding house and office examples with a variety of equipment efficiencies
and energy costs. Indoor fan energy is not usually included in equipment efficiency ratings, so allow 10%
extra for residential air handlers and 20% extra for commercial air handlers
with longer duct runs.
The
equations are given below:
|
House:
Estimate #1
Heat
with oil at $1.00 per gallon and a furnace that is 70% efficient. Cool using
electric equipment with a SEER of 8; electricity costs $0.10 per KWH. (1 gal.
oil = 140,000 BTU; SEER 8 = 8 BTU/watt)
House: Estimate #2
Same
example, but use a heat pump with a COP of 2.5 and a SEER of 7. (COP 1 = 3,400
BTU per KW)
|
Office: Estimate #1
Heat
the office building with natural gas that is 70% efficient at $0.50 per thermal;
cool with electricity at $0.10 per KWH and SEER 9. (1 therm = 100,000 BTU)
|
NOTE:
The
preceding calculations can be applied with some confidence to residential and
smaller commercial occupancies. However, they do not apply to 24 hour a day occupancies like hospitals or airline
terminals. Large buildings that operate chillers, cooling tower fans, cooling
tower pumps, chill water pumps, high velocity air supply fans, and return air
fans; may have overall operating SEER's as low as 2 or 3.
|
5.2
Evaluating Energy Conserving Alternatives
Preceding
pages proposed a method for estimating annual heating and cooling costs. The
same method may be used to evaluate energy conserving alternatives. Calculations
are based on the office building example used earlier in the text for heat gain
and loss estimates (p. 18 and 28). Alternates #1 thru #4 assume 1,600 full-load
hours for annual heating and 1,400 full-load hours for cooling; alternate #5
uses 1,500-full load hours for heating and cooling.
Alternate
#1: Slab Edge Insulation
An
insulation contractor proposes to reduce building heat loss by installing slab
edge insulation for $3,000. Evaluate the proposal by finding the firstyear on
investment.
Given;
Slab
Edge length is 494 linear ft. (allow 1 sqft. per linear ft.)
U
value without insulation is 0.8, with insulation U is 0.1. Winter TD is 60°F.
Heat
is electric resistance at $0.08/KWH (each KWH yields 3,400 BTUH).
|
|
|
Alternate
#2: More Roof Insulation
The
roofing contractor offers to increase the thickness of urethane roof insulation
from 3" to 4" for $2000. Evaluate this proposal by finding the firstyear
return on investment.
Given:
Roof
Area is 10,800 sqft.,
U
value for 3" roof is 0.05, U value for 4" roof is 0.04; winter TD is
60°F, summer ETD is 36°F. Heat with a 80% efficient gas furnace with gas at
$0.75 per therm.
Cool
with an SEER-7 unit; electricity costs $0.09 per KWH.
|
Alternate
#3: Reduced Fresh Air
The
HAC consultant proposes to weatherstrip the building and reduce the ventilation
rate to 10 CFM per occupant (a total of 1,6000FM). Added costs for controls and
weatherstripping total $2,000. Estimate the first-year return on investment.
Given;
Old
design: 2,970 CFM winter, 2,400 CFM summer. New design: 1,600 CFM for both
winter and summer.
Winter
TD is60°F; summer TD is 20°F, GD (Grain Difference) is 40.
Heat
with a 75% efficient oil fired boiler using $1 per gallon oil.
Cool
with a SEER-8 electric chiller, electricity costs $0. 07 per KWH
|
Alternate
#4: Reflective Windows
The
glazing contractor proposes to provide reflective windows instead of clear
windows for $2,470 extra. Evaluate this proposal by estimating the first year
return on investment.
Given:
Shading
Coefficient (SC) for non-reflective glass is 85%; SC for proposed reflective
glass is 45%. Solar Factor (SF) in summer months is 30 (for north and shaded
south glass). Glass Area is 2,470 sqft.
Cooling
SEER is 7, and electricity costs $0.10 per KWH.
Alternate
#5: Improved Heat Pumps
The
HAC subcontractor proposes to furnish more efficient heat pumps for $10,000
extra. Evaluate this proposal by estimating the first-year return on investment.
Given:
The
standard heat pump has a COP of 2.1 and an SEER of 7.3; the high efficiency heat
pump has a COP of 2.8 and an SEER of 11.1. Building heat loss is 323,600,000 BTU
per year. Building h eat gain is 945,000,000BTU per year (Note: 1,500 full-load
heating and cooling hours are used to calculate BTU per year for this example).
Electricity costs $0.08 per KWH.
|
|
*
Estimates of annual cooling savings based on reduced peak heat gain may be
exaggerated because of solar load variation. More accurate projections may be
developed using actual solar data for the building site.
2.6
Office Example, Heat Loss Calculation
|
Design
Conditions
Winter
temperature is 10°F (for location "0" on map p. 14). An indoor
temperature of 70°F is assumed; temperature difference (TD) is 60.
Project
Conditions
Fresh
Air:
estimate infiltration at 0.75 air changes per hour in winter (0.5 air changes
per hour in summer). Estimate ventilation rate at 15 CFM per person. Fresh air CFM due to infiltration is the largest
value in winter. (p. 10) Glass: double glass; U = 0.6 (p. 9)
Lighting
o not take heat gain credit because lights will be off on cold nights.
People:
estimate 160 occupants, but do not take heat gain credit because people are
absent on cold nights.
Ceiling-Roof:
detail is below; U = 1/R total = 0.05 [1/(0.2+18+0.7) = 1/18.9 = 0.05] (p. 9)
Wall:
see detail below; U = 1/R total = 0.07 [1/(0.2+0.4+1+0.5+11+0.5+0.7) = 1/14.3 =
0.07.]
(p.
9)
Floor:
slab on grade; factor is 2 BTUH per sqft. (p. 13)
Slab
Edqe: (not shown) no
insulation; no heating ducts; U = 0.8 (p.
13)
Doors
Single glass; U = 1.1 (p. 9) Equipment:
Do not take a heat gain credit for equipment because it does not operate on cold
nights.
Quantities
See
Plan and Detail at left for dimensions. Fresh Air: building volume is
(21,600)(11) _ 237,600 CF. At 0.75 air changes per hour the expected
infiltration is (237,600+60)(0.75)= 2,970 CFM. Ventilation rate for 160 people
at 15 CFM each is 2,400 CFM. Use the larger infiltration value for winter heat
loss.
Glass:
windows are 4' high; total window area is 2,400 sqft.
Ceiling-Roof:
area is half floor area (2 floors) or 10,800 sqft..
Walls:
net wall is 10,880 sgft. Gross wall area is 10,950 sqft.; add for soffits and
sills 2,400 sqft.; deduct for windows and doors 2,470 sqft. Floor: slab
on grade area = 10,800 sqft. Slab Edge: 494 linear feet.
Doors:
2 @ 5'x7'= 70 sqft.
Winter
Heat Loss = BTUH
Insert
appropriate U values, constants, factors and temperature difference; then
complete calculations and total BTUH. Add 10% if ducts are outside the conditioned space.
2.12
Office Example, Heat Gain Calculation
|
Design Conditions
Maps
show a summer dry bulb temperature of 95°F and a wet bulb temperature of 76°F
(p. 14, location "0"). Desired indoor conditions are 75°F and 50%
relative humidity. Time of peak heat gain is estimated as 4 P.M. Temperature
difference, TD = 20; and grain
difference, GD = 40 (p. 23).
Project
Conditions
Fresh
Air:
select largest of infiltration at 0.5 air changes per hour or ventilation at 15
CFM per person (p. 10).
Glass:
double glass U = 0.6. The (SC)
shading coefficient for clear double glass is 0.85
(p. 22). Lighting: estimate 3 watts per sqft. of floor area for this
office occupancy, and revise as necessary after completing lighting design.
Office building lighting installations can range from 1 to 6 watts per sqft.
depending on luminous intensity, lamp type, and fixture design.
People:
160 occupants seated doing light work. Ceilina-Roof: U =
0.05; weight is 7 pounds per sqft.; color light. ETD = 36
(p. 22). Walls: U = 0.07; weight
is 45 pounds per sqft.; color dark. The west wall is hot at 4 P.M.; its ETD is
40; the weighted average ETD for all walls at 4 P.M. is 23 (p. 22).
Doors:
U = 1.1 (tempered single glass). Solar gain for doors is included in
Glass. Equipment: Allow 1 watt per sqft. for electrical equipment
operating at the time of peak heat gain. Also allow 10 hp. for air handler fans.
Quantities
Fresh
Air:
use largest value. Infiltration at 0.5 air changes per hour = 1,980 CFM,
(21,600)(11)(0.5)+60 = 1,980.
Ventilation
at 15 CFM per person = 2,400 CFM, (160)(15) = 2,400.
Glass
1,030 sqft. faces north (includes 70 sqft. of glass door area);
1,440 sqft. faces south. Lie h in : totals 64,800 watts at 3 watts
per sqft. People: each occupant produces 250 BTUH
sensible
plus 150 BTUH latent. Ceiling-Roof : area is 10,800 sqft. Wall:
net wall area is 10,880 sqft.
Doors:
area= 70 sqft.
Equipment:
allow 21,600 watts at 1 watt per sqft.; plus 10
hp. for air handler fans.
Summer
Heat Gain = BTUH
Insert
appropriate factors and temperature difference; then complete calculations and
total BTUH. Add 10% if ducts are
located outside the conditioned zone.
Refer
back to heat loss example on page 18 for more detail.
Heat
Loss - Heat Gain, Summary
|