(pressing HOME will start a new search)
|
|
METHODS OF SCHEDULE COMPRESSION
Gary
B. Gehrig |
The
next 10 years are going to be exciting times in the construction industry.
Changes are occurring at a very rapid pace. New technology, a world economy,
better informed owners, and keener competition are but a few of the initiators
of this change.
We,
as a society, are expecting and demanding that things be done faster. The speed
limits on the rural interstate systems have been raised to 65 miles per hour so
that we can drive at 75 miles per hour. The computer industry is technologically
capable of creating hardware which can
perform functions on personal computers micro seconds faster with each new
machine placed on the market. The user wants an AT instead of an XT because the
wait of a few seconds is too disturbing. The veterans of the construction
industry can remember the days of slide rules and Frieden calculators; however,
impatience has driven slowness from the scene.
Estimates
are prepared faster, schedules are developed faster, and the flow of information
during the construction process is faster. But what about the actual design and
construction of the project? The demands and expectations to reduce the time of
the project cycle are real. The industry must simply do this! The owner or user
of construction develops a new product and has to get it on the market to
maintain the competitive advantage. The architects and engineers must generate
high quality designs and documents in less time to survive in this world economy
where the Asian and European competition is intense.
In
1986, the Construction Industry Institute (CII) undertook a study of the methods
used in the industry to compress construction schedules. The research for the
study was conducted in the Construction Management program at Colorado State
University. In order to have a base of reference for the study, a definition of
schedule compression had to be agreed upon by the CII and the researchers.
Schedule compression was subsequently defined as:
A
reduction from the normal experienced time or optimal time typical for the type
and size project being planned within a given set of circumstances.
A
vivid example of this definition was related by three project managers from
Ferguson Construction, Cleveland, Ohio. A repeat client had a project with a
normal experienced construction time of 17 months. The project was delayed three
months by the owner but the expectation was still to complete the project in the
14 months remaining in the clients schedule.
OBJECTIVES OF THE STUDY
The
objectives of the study were:
|
FOCUS OF THE STUDY
The
study includes schedule compression techniques that will reduce project time as
well as techniques that will. prevent needless loss of time once the project is
started. The proactive techniques are part of the planning process. The reactive
techniques are part of the problem solving aspects of the project.
METHODS OF RESEARCH
A
modified form of the Delphi Technique was selected for the research methodology.
An extensive literature search was conducted using both the university systems
and private industry library resources. An identified population of experienced
project managers, estimators, schedulers, and cost engineers was interviewed by
telephone. From the literature searches and from the conversations, a list of
schedule compression techniques was compiled. The techniques were categorized
and placed on a survey form which was sent to the original interviewees as well
as the Planning and Scheduling Committee of the American Association of Cost
Engineers. These individuals were asked to subjectively rate each technique as
to its impact on duration and cost when applied at the various phases of the
project cycle. The CII Cost and Schedule Taskforce were then asked to review the
survey results for reasonableness and concurrence.
The
initial intent of the study was to identify those techniques being used in the
industry to compress schedules during the construction phase of the project.
Very early on, it became apparent that the time of construction is influenced by
decisions and choices made by the project management team in both the design
phase and the procurement phase of an EPC project. The input and output factors
that affect the choice of a particular method of compressing schedules are shown
on Figure 1.
A
project team desirous of selecting a method must consider the organizational
variables, project variables and application methodology variables that will
influence the success or failure of a selected method. In addition, management
must consider all the project activities that will be impacted by the method
when applied and make a prediction of the possible outcomes of the action.
RESEARCH ACTIVITIES
The
Principal Investigator interviewed about 28 experienced project managers,
estimators, schedulers, and cost engineers by telephone. A short questionnaire
was used to start the interview; however, most of the research data was
generated when the interviewee started to talk freely about past experiences.
The interviews continued until the investigator was satisfied that no new
techniques were being uncovered. The telephone interviews were
stopped
after the 28th individual because the techniques being expressed tended to be
repeats of techniques already received.
The telephone conversations were analyzed and approximately 200 identifiable techniques were extracted. Further analysis revealed the 200 techniques could be placed in eight distinct categories as listed below.
|
Some
of the methods could be classed as "Motherhood and Apple Pie" and some
methods are truly innovative and creative. The catalog of methods includes all
methods.
To
develop a workable survey instrument, the 200 techniques were combined into 74
techniques. This is the smallest number of combinations the researcher felt
maintained the identity and intent of the original 200 techniques. The
respondents were asked to subjectively rate each of the 74 techniques as to
their impact on cost and duration when applied at the seven phases of a project.
|
The
survey was mailed to the respondents in two sections to minimize the
time and effort required to complete the survey. The second section was mailed
about two weeks after the first section. Sixty percent of the surveys were
returned to the researcher.
The
results of the survey were complied on Lotus 123. A research source document is
available from CII and contains all results of the research project.
METHODS OF SCHEDULE COMPRESSION
(Note
that more than 74 techniques are included in this paper. The CII taskforce has
included some of the original 200 methods in the report and some techniques
identified after the survey was completed.)
Due
to the number of schedule compression techniques and the limitation on the
number of pages allowed in this paper, the techniques are listed without
definitions and other clarifying statements. The CII source document and the CII
|
Figure
1 |
Executive
Summary of this research project contain a full text complete with definitions
of all the techniques.
All
schedule compression techniques have a set of graphs depicting the impact of the
technique on cost and duration when applied at the seven phases of a project
cycle. Over 1000 graphs were generated by Lotus 123 during the analysis of the
research data. Only a few of the graphs are displayed in this paper. The CII
source document for this research project contains all the graphs for all the
techniques.
1.0
Engineering Phase
1.01
Change Management System During Design.
1.02
Computer-Aided Design and Drafting (CADD).
1.03
Consolidation of Permanent Components or Functions.
1.04 Constructability Analysis During Engineering.
1.05
Dual-Purpose Design. 1.06 Efficient Packaging for
Transportation.
1.07
Engineering Approvals. 1.08 Evergreen Contract.
1.09
Freezing of Project Scope. 1.10 Inter-Stitial Design.
1.11
Materials, Equipment and Systems
Standards.
1.12
Multiple Prime Contracts.
1.13
Non-Traditional Drawing Release.
Figures
2 through 8 shows what occurs when three diverse points of view are expressed in
one survey. Construction project managers strongly supported the idea of
releasing engineering drawings in stages as portions of the drawings are
completed. They felt that the engineers hung on to the drawings too long
resulting in needless design and drafting. On the other side, the engineers felt
the field people make too many mistakes if the drawings are not completed at a
high level of detail.
The
survey results depicted on the seven graphs change from a relatively flat curve
skewed by a strong feeling of moderate increased cost in the early engineering
phase, Figure 2, to a typical bell. curve configuration shown on Figure 7
representing the final 25* of construction.
|
Figure
2 |
|
Figure
3 |
|
Figure
4 |
|
Figure
5 |
|
Figure
6 |
|
Figure
7 |
|
Figure
8 |
1.14
Off-the-Shelf Components.
1.16
Parametric Estimating.
1.16
Permanent Facilities Used for Construction Purposes.
1.17
Physical Modeling.
1.18
Specification Review.
1.19
Standard or On-the-Shelf Designs.
1.20
Vendor/Engineer Early Information Exchange.
2.0
Contractual Methods
2.01
Contract Document Review.
2.02Fair
Risk Assignment.
2.03
Fast-Track Scheduling.
2.04
Improve Contractor Cash Flow.
2.05
Incentive Programs.
2.06
Lump Sum Contracts.
2.07
Minimize Owner Involvement.
2.08
Partnering and Team Building.
2.09
Prequalification.
2.10
Reimbursable Contracts.
2.11
Work Subject to Owner Approval.
3.0
Field Organization
3.01
Area Coordinators.
3.02
Assistant Field Project Manager.
3.03
Efficient Staffing.
3.04
Materials Coordinator.
3.05
Safety/Loss Control Program.
3.06
Well-Defined Organizational Structure.
4.0
Planning and Scheduling.
4.01
Adaptation to Weather Conditions.
4.02
Avoidance of interruptions.
4.03
Pareto's Law Schedule Management.
|
Figure
9 |
|
Figure
10 |
4.04
Planning.
Ensuring
that all work benefits from planning was the technique believed to have the most
potential for schedule compression. Figures 9 ENGINEERING 0 to 26% and Figure 10
CONSTRUCTION 0 to 25% indicate a strong belief that planning could significantly
decrease project duration and significantly decrease project cost at the same
time.
4.05
Realistic Scheduling.
4.06
Reduction of Task Scope.
4.07
Repetitive Tasks Scheduling.
4.08
Schedule Crashing.
4.09
Startup-Driven Scheduling.
4.10
Use of Float Flexibility.
5.0
Materials Management
5.01
Chief Executive Office (CEO) Commitment.
5.02
Dedicated Truck Shipments.
5.03
Just-In-Time Material Deliveries
5.04
Laydown Area Assignment.
5.05
Material Identification on
Purchase
Documentation.
5.06
Owner-Furnished Materials.
5.07
Prime Contractor-Furnished Materials.
5.08
Prioritize Procurement.
5.09
Product Identification.
5.10
Shared Material Takeoffs.
5.11
Special Material Handling Crew.
5.12
Transportation System Review.
5.13
Vendor Submittal Control.
6.0
Work Management
6.01
Advanced Construction Equipment.
6.02
Change Management During
Construction.
6.03
Constructability Analysis During Construction.
6.04
Critical. Equipment Contingency Planning.
6.05
Field Models.
6.06
Job Site Pre-Assembly.
6.07
Making Site A Good Place to Work.
6.08
Modern Management Systems.
6.09
On--Ground Pre-Assembly.
6.10
Site Layout.
6.11
Special Network Analyses.
6.12
Staged Pre-Positioning. 6.13 Tool Management.
6.14
Work Sampling.
7.0
Personnel/Labor Management
7.01
Continuity of Work Responsibility. 7.02 Craft Worker Bonus/Award Program.
Figure
11 is representative of the feeling of the respondents that any of the
PERSONNEL/LABOR MANAGEMENT techniques could result in a decrease in duration but
with an increase in project cost.
|
Figure
11 |
7.03
Crew Pre-Work Briefings.
7.04
Crew Training and Rehearsals.
7.05
7.05 Cross-Training.
7.06
7.06 Labor Minimization.
7.07
Participative Management.
7.08Personnel Management Practices.
7.09
Project Agreements.
7.10
Rolling Shifts.
7.11
Scheduled Overtime.
7.12
Specialty Shifts.
7.13
Spot Overtime.
7.14
Supervisor/Worker Ratio.
7.15
Team Building.
8.0
Start-Up Phase
8.01
Minimize Scope of Start-Up. 8.02 Temporary Startup Systems. 8.03 Startup
Planning.
CONCLUSION
The
end product of the research project is a catalog of methods of schedule
compression. The publication is not a "How to do it" book because
there are too many variables involved in the decision making process. Each job
has to analyzed as to the job specific parameters or characteristics. The
application of the techniques must be based on subjective appraisals of the
situation by the professional constructor.
No
mention of scientific methods for compressing schedules is made directly.
Techniques such as linear programing and probability analysis are included
within other techniques. In general, the interviewees did not use scientific
methods in their daily activities.
The seven methods with the most potential for reducing the project schedule in all phases of the project cycle are:
1. Upfront planning
2. Early client approval of project scope
3. Work on the right activities - Pareto's
4. law
5. CPM Network techniques
6. Prioritized procurement
7. Team concept
8. Minimize client interference
Many
ideas have been tried in the industry to shorten construction schedules. Maybe
one of the methods identified in the study will contain the clue to trigger the
thought process and lead to decisions resulting in the desired reduced time.