(pressing HOME will start a new search)

 

Back Home

ASC Proceedings of the 31st Annual Conference
Arizona State University - Tempe, Arizona
April 6 - 8, 1995          pp 87 - 94

 

Using Computers to Simulate the Construction Bid

 

Stephen P. Mead

Department of Construction Management

East Carolina University

Greenville, North Carolina

 

One of the challenges facing construction educators is preparing students for the construction bid process. In today's diverse building environment, where contractor's rely heavily on specialized subcontractors and vendors, bidding has become one of the largest components of the estimating process. Unfortunately, it is difficult to simulate the time intensive pressures of the bid process in the classroom. This article discusses the how to use a networked classroom computer system to simulate the construction bid process.

 

Keywords: Construction, Estimating, Bidding, Computers, Simulation

 

 

Introduction

 

Recent studies indicate that one of the most important competencies which are developed in Construction education programs is estimating. One of the participants in a recent study commented, "We need people who can contribute to the bottom line."(Mead, Gehrig, 1994). Of course the profitability of a project is generally a result of the accuracy of the estimating process. As a result, a solid understanding of estimating technique is essential to the success of future constructors.

 

In the past most contractors approached estimating much like it is taught in the class room. Each brick or stick was quantified then priced, the prices were summarized and a profit was added to the bottom line. This system worked well when the majority of a contractor's work was self-performed. But over the last twenty years, contractors have moved toward "brokering" much of the project work, and its associated liability to subcontractors. As a result, soliciting and analyzing sub quotations has become one of the largest components of the general contractor's estimating process.(White, G.L. 1993)

 

In the past, educators have struggled with establishing an environment which approximates what happens in a general contractors office on bid day. While recent developments in estimating laboratories and construction simulation centers can help facilitate the bid process, it is difficult to establish an environment which approximates the chaotic atmosphere of a general contractor's bid room. Fortunately. computer technology may be able to help educators simulate the rapid fire exchange of information which occurs during the bid process.

 

Today’s Bid Environment

 

Lets look at what happens during a construction bid during the two hours before the bid is due. Most contractors handle bid day with a team of estimators, project managers, and support staff. Using the plans and specifications this team collects all of the information needed to price the job. In today's subcontract intensive environment, a large part of the bid is collecting and digesting subcontractors quotes. (J. Morrisey, Personal Communication 1994)

 

These quotes each contain important pieces of information. Most obvious is the subcontractor's price. This bottom line number may contain allowances for taxes, bonds, insurance and wage rate requirements, as well as the material and labor costs of the work. Each quote may also contain unique information on the subcontractors qualification and exclusions, and scheduling information on the subcontractor's work.

 

During a typical bid, the estimating team handles hundreds of sub quotes. The quotes arrive through the mail or over the fax, and some quotes are delivered personally to the contractor's office. Additionally, many subcontractors give their quotes over the phone, then follow up with a written copy of the proposal once the bid is complete.

 

In this era of bid cutting and shopping, many electrical and mechanical contractors wait until the last possible moment to phone in their quotes. This helps protect their number from bid shopping during the bid process, but it puts additional pressure on the estimating team in handling last minute prices. In today's competitive marketplace it is not unusual to process five hundred quotes in the two hours before bid time.(Engineering News Record, 1992)

 

Scoping: Handling Sub Quotations Efficiently

 

How do organized contractors handle this chaotic process? In two ways. One, many contractors take sub quotes, then compare each subs scope of work, pricing and scheduling information with other subs quotes in that category of work. This "letting the chips fall where they lie" method saves contractor's time at the front end of the bid process, but often fails to uncover omissions or duplications of work between subs.

 

Another approach is called "scoping". Here, the estimating team reviews the plans and specifications and develops a list of work which they feel should be completed as part of each division of work. This list is then distributed to each sub prior to bid time, or discussed with the sub when the quote comes in. Generally, scopes are placed in spreadsheet

 

format, with the names and numbers of the subs along the top of the sheet, while the work items are listed in the first column.

 

The scoping process forces estimators to review and understand the project at its most detailed level. As such. this review helps contractor's eliminate scope overlap between subs, and also helps define the contract between sub and contractor once the bid is complete. Score sheets enable estimators and their staff to collect and analyze information quickly, and they provide a way of graphically comparing one subs work to another.

 

For instance, if a subcontractor misses an item of work, the estimator circles the omission on the scope sheet. Estimators call these omissions "holes." Using another sub's detailed quote, or a price generated in - house, the estimator then fills the hole with a "plug number". This helps estimators analyze and compare different bids. Once all of the holes are filled with plugs, the estimator can analyze each bid for the best complete price. In this way, organized estimators collect and analyze qualifications, exclusions, and pricing during the chaotic moments that lead up the bid.

 

Other Complications: Unit Pricing and Value Engineering

 

The bid process is further complicated by Architects and Owners increasing requests for unit pricing and value engineering suggestions. Over the past 10 years, owners and architects have asked contractor's to break down their lump sum prices into more understandable unit costs. Unit pricing helps "nail down" pricing for change order work, and also serves as a cost comparison between bidding contractors.(J. Morrisey, Personal Communication, 1995)

 

As an example, architects often ask contractor's for unit costs on duplex electrical outlets. In turn, the contractor asks each of his electrical subs to provide a unit cost for duplex outlets at bid time. When the costs arrive, the contractor adds a markup for overhead and profit to the subs unit cost, then submits the new unit price as part of the bid. While this seems simple, it is not unusual for an architect to ask for 20 or thirty unit costs as part of a contractors bid. Assembling these costs in the final minutes of the bid process, puts a lot of pressure on the estimating team.

 

Figure 1.  Master Scope

 

Value engineering also complicates the bidding process. Increasingly, specifications call for value engineering suggestions as part of the contractors bids. As a result, estimators and their subcontractors have to assess the work for constructability and make value engineering suggestions to the owner. These suggestions have to be analyzed and included as part of the bid package to the owner. (O'Brien, 1994)

 

Finally, the estimating team is also responsible for administering the terms of the bid. That is, estimators have to take care of insurance certificates, bonding requirements, and completing the bid form and envelopes. Bid forms are often complicated legal documents which require an estimators careful scrutiny.

 

The accuracy of the estimator's work in the intense, demanding minutes before a bid is due, often define the profitability of the project. Typically, most of these details come together in the pressure filled hours before a bid is due. As bid time draws near, the estimating team assembles the sub quotes, unit costs, and value engineering suggestions into the bid package. Additionally, they complete the bid forms, attach bonding documents and assemble qualifications and exclusions to the bid. Faxes arrive, phones ring, scopes are compared, negotiations are made. At the last moment, the price is given to the bid runner, who sprints to the architect's office to deliver the bid.

 

Simulating the Bid Process in the Classroom

 

Some Limitations

 

Many university construction programs don't have the facilities required to simulate a realistic construction bid. Today, most contractors use state of the art phone systems, fax machines, and computer systems to move estimating information during the bid process. Given declining resources, most construction education programs can't dedicate the space or the equipment required to replicate a contractor's bid room. In most cases, it isn't practical for a department to set up a phone or fax system which will be used solely for estimating bid projects.

 

Attempts have been made to simulate the process by forming student teams, who act as independent contractors on a specific set of plans and specifications. Using a script prepared by the class professor, volunteers submit bids and clarify scopes with each of the class estimating teams. (Kirk, Khattab 1993) Another approach is to provide the estimating teams with detailed written proposals for each subcontractor an hour prior to the bid time. The teams then analyze each of the proposals to determine which subcontractor has a complete scope of work and the best price.

 

But both of these approaches have their limitations. In the first case, subcontractors have an intimate knowledge of each specific project which comes from preparing a detailed estimate of the work. As such, volunteer instructors don't have the project knowledge required to make informed decisions on the complexities of price and scope of work. They can't answer pertinent questions which typically come up during the bid process like, "Will you furnish but not install the anchor bolts listed on the plans?" From an instructors viewpoint, organizing the volunteers and their quotations also takes a lot of time and effort. Like most real world construction bids, things have away of going haywire.

 

The second approach. which uses written quotations, allows the estimating team to work with detailed subcontractor proposals. Unfortunately, in real world bidding situations, the subcontractor proposal never arrive at the same time. Quotations arrive via the fax machine, over the telephone, via the mail, and increasingly through electronic links. In today's competitive world of bid cutting and shopping, it is not unusual for a contractor to receive all of their electrical and mechanical quotes fifteen minutes prior to bid time. Moreover, written quotations precludes using phone quotations during the bid. These "audio" communications between contractor and subs are integral to the modern bidding process.

 

A Simulation Study

 

Project Description

 

Over the last two years, we have used the plans and specifications for a commercial project with a construction cost of about $1,000,000. The project includes a cooling tower basin and mechanical auxiliary building for a power generation facility at a major university. This project was completed in 1992, and the contractor has given our program the complete bid and historical costs on the project.

 

At the start of the class, each student buys a set of the plans, and the course pack for the class. The project specifications are incorporated in the course pack for the students use. During the estimating class, these plans and specs are used to develop quantity surveys, specification summaries and unit pricing for individual divisions of work. This process helps get the students familiar with the project prior to the bid exercise.

 

Forming Student Teams

 

The bid exercise takes about two weeks. In the first week, the students are divided into teams of three members. Based on student performance, the instructor designates one of these members as a chief estimator. The chief estimator is asked to organize and schedule the bid and delegate tasks to other team members. To encourage competition, we ask each of the teams to form a company, with a company name and logo.

 

During the first week, students attend a mock pre bid meeting, where our instructors act as architect, engineer, and owner's representative. Before the meeting, we ask each of the teams to review the plans and specifications and develop a list of estimating questions on the project. At this meeting each team is given a list of qualified subcontractors and a "bid package" which includes the bidding documents, bonding and insurance requirements, and unit price sheets. We also hand out a check list of items which will be used to analyze each bid in terms of presentation, accuracy, and completeness.

 

During the mock meeting, we field questions about site conditions, the soils report and Davis/Bacon wage standards. To help develop each team's understanding of general conditions cost, we also review the requirements for schedule, safety, and liquidated damages.

 

Student Bid Development

 

Over the next few days, we ask the students to develop scope sheets on each division of subcontracted work. To refine the student's estimating skills, we ask each team to "self perform" the concrete work required on the project. This forces the students to research and develop quantity surveys and work packages using prevailing wage and material costs. Additionally, each team develops a general conditions cost estimate using the project schedule outlined at the bid meeting.

 

Typically, one team member handles the marketing side, assembling the qualification statement and the presentation package for the bid. Another member handles the computer input and unit price development. Finally, the chief estimator completes the bid form and secures bonds and insurance from one of our instructors who acts as the surety for the project. We encourage the teams to meet all the details ofthe bid, including value engineering recommendations, qualifications and exclusions and the appropriate notary and corporate seals

 

Instructor's Chores

 

While this is going on, the instructor assembles subcontractor proposals for each of the subs on the bid list. Using the historical costs from the job, we develop about twenty five proposals - three or four in each category of work - using computer spreadsheets. We modify the proposals by omitting scope items or including unnecessary work or taxes. These modifications put "holes" in each subcontractor's quote, camouflaging the best price in each category of work. Once the spreadsheet is complete, we save each sub's quotation as an individual file. Each file contains the subs price, unit costs, scope of work and specific qualifications and exclusions for the project. (Insert figure 2 here)

 

Figure 2.  Subcontractor Quote Sheet

 

Electronic Links

 

Thanks to computer technology and digital communication, we can now help prepare students for the chaos which occurs during the bid process. At our University, we are fortunate to have a network which ties together instructors with the student labs, and our colleagues within the school. In turn, that network is linked with the Internet, and of course the world's computers.

 

Internally, we use the network to process communication, via E-Mail. We also use the system to transfer information to our computer presentation centers and our student computer labs. For instance I can transfer files from my computer to the lab via our public exchange directory or to individual computers in the lab. Additionally, we can send files to the lab printers which act as a simulated fax machines on bid day.

 

Bid Day

 

Generally, we schedule the bid for 11:30 AM on Friday, the day we have the least amount of lab activity. Student teams assemble at the computer lab, and we begin simulating the bid at around 8:00 AM. Here is where the fun begins.

 

We start by loading several of the proposal files into the public exchange directory. The teams have instant access to the exchange, and they pull up and review the sub proposals we have placed there. Next, we fire off a few faxes to the lab printers. At specified intervals, we also forward individually tailored proposals to each of the student team via their team directories. The students have to field the proposals, and then use the scope sheets to analyze the information they have obtained.

 

At around 9:00, things get pretty chaotic, so we send E-Mail messages from the owner/architect which ask the teams for some specific, and previously unasked for, breakdowns on their concrete prices. Finally, thirty minutes before the bid, we send an instructor to the lab. He hands out an extremely attractive price from a subcontractor who wasn't on the bid list.

 

Student/Instructor Interaction

 

During the bid, the teams communicate with the instructor with E-Mail messages. The instructor can use E-Mail to fire off messages like, "Did you remember to include an allowance in your general conditions cost for de-watering?" In turn, the students use E-Mail to send messages to specific subcontractors-via the instructor-to clarify scope and price. This electronic dialog creates an exciting, and sometimes agitated, communication between students and simulated bidders. We use the phone in the laboratory as the "hot line" to the instructor, which is only to be used in extreme emergencies.

 

Generally, the students assemble their pricing using electronic spreadsheets, or with Timberline, a construction software application. The "marketing" team member assembles the presentation, a runner delivers the bid, someone operates the computers, and the chief estimator manages and supervises the process.

 

At 11:30 sharp we hold a public opening in our school conference room. Instructors posing as the Architect, Owner, and Engineer, stamp the bids as they arrive and scrutinize the bids for the details. The team quotes are then read aloud, and then we discuss what happened during the bid process.

 

Evaluation

 

We evaluate the student teams using two components, a team grade and an individual grade. We formulate the team grade using the evaluation checklist that is handed out at the pre-bid meeting. This checklist outlines the criteria for timeliness, accuracy, documentation, presentation, and organization.

 

We ask the students to review and attach the completed checklist to their proposals. After reviewing the proposals, the instructor assigns points to each of the criteria. In turn, these points form the team grade for each proposal.

 

After the bid is completed, we ask each team member to evaluate the other members of their team for their contribution to the bid effort. This form asks students to assess each other in terms of leadership, time management, communication skills, teamwork, and professionalism. The students rate themselves on a scale of one to ten in each category. The points are then totaled and averaged for each student. This average score then becomes the individual grade for the project.

 

Figure 3.

 

Other Ideas & Improvements

 

Like bids in the real world, we always have a few crises. But most of our students do an admirable job handling the rapid fire exchange of information and molding the information into a single price. We are, however experimenting with some improvements.

 

One idea is to streamline the delivery process for the instructor. Scheduling shareware like Timeroo allows you to attach file transfer activities to your computer's clock. As such, you can transfer electronic proposals at specific times during the bid. Scheduling software frees the instructor from generating all of the bids, and leaves time for trouble shooting and student consultation.

 

Also, if you adopt a standard format, advanced spreadsheet programs like Excel can help you assemble a database of bid proposals and bid scenarios which can be used again and again. Somewhere in the future, we would also like to incorporate an electronic voice mail system which will help us generate quotes phone quotes to teams in the laboratories.

 

Finally, we have decided to hold the bid opening off campus this year, which should force the student teams to deal with a remote bid runner who can only be reached by telephone.

 

Conclusions

 

Simulating the bid process can help students in several ways. First off, the simulated bids enable students to experience the time intensive pressures associated with the bid process. Students have to collect multiple bids, and analyze those disparate bids for scope of work, price, taxes, insurance and bonding requirements, unit pricing and value engineering. Like a contractor's bid room, this process take: place during a compressed time frame. forcing student teams to solve problems and make decisions under pressure.

 

Secondly, the simulated bid gives students an opportunity to work with computer technology. During the bid process, student teams work with estimating software, electronic data interchange, and E-mail systems. As a result, students learn how computers and digital technology can be used effectively in contractor's offices.

 

Most importantly, the simulated bid helps students under­stand how construction teams work during the estimating process. This "teambuilding" effort helps show students how work is delegated and managed by individuals acting as a unit. Teamwork helps improve student's interpersonal skills in oral and written communication. Additionally, the team leaders are given valuable experience managing a group. Groups also learn important lessons about what happens to team efforts when any part of the process fails.

 

Figure 4.

 

 

References

 

Engineering News Record, "Shop Till they Drop" Engineering News Record March 9, 1992. pp 26 -28

 

Kirk, Max W. and Mostafa Khattab, "Advanced Cost Estimating and Project Scheduling Laboratory" American Society for Professional Estimators (ASPE) May/June 1993

 

Mead, Stephen P. and Gary Gehrig, "Skills for the 21st Century: What Constructors Need to Know." American Professional Constructor. Volume 18, Number 3. September 1994

 

O"Brien, James, J., Preconstruction Estimating. McGraw Hill Inc. New York N.Y. 1994. p319 -323

 

White, Gary L.,"Estimating- It's an Art too." presentation to the Associated General Contractors of America. Washington D. C. Ocotber 1993.

 

 

Figure 5.

 

 

Go to the  Home page for:
bullet ASC Annual Proceedings
bulletJournal of Construction Education
Associated Schools of Construction Proceedings of the Annual Conference.  Copyright 2003
For problems or questions regarding this web contact Tulio Sulbaran, Proceedings Editor/Publisher.
Last updated: September 09, 2004.