(pressing HOME will start a new search)
Retainage
Policies of Public Agencies,
Findings
of a Questionnaire Survey
Department
of Construction Management
Florida
International University
Miami,
Florida
This
paper presents a discussion and findings of a questionnaire survey on
the issue of retainage. Traditional retainage practice and its
variations, effects of retainage under the prevailing economic reality,
and viable alternatives are discussed in the paper. The issue of
retainage is presented from the perspectives of different groups that
make up the construction industry. Opinions and suggestions of the two
diverse groups, public agencies and general contractors, are included.
These results were developed through a questionnaire survey conducted in
the state of Florida. The two groups differ widely on the issue of
retainage. It was observed, however, that relaxation of the conventional
fiat 10 percent retainage practice in public construction projects is
now a trend being increasingly adopted by many public agencies. General contractors feel that the 10 percent retainage hurts their cash flow and can be relaxed since the owner is protected by bonding. Owners, on the other hand, think bonding is too difficult and time-consuming to invoke if the contractor is unwilling to finish the project. In such situations, retainage provides a practical way of solving the problem. Many respondents from both groups agree that a mechanism for paying interest on the retained money to the contractors should be devised and practiced. Other alternatives, such as, a sliding scale of decreasing rate of retainage, 5 percent or no retainage after 50 percent completion, and retainage of actual amount to complete unfinished portions of the project were favored by a considerable number of respondents. Keywords: Construction Contracts, Retainage, Public Construction. |
Introduction
Like
many other industries, one of the main problems in construction is insufficient
capital. This lack of capital in the industry, along with some
standard-but perhaps outdated-business practices, greatly enhances
the problems of inadequate cash flow needed for the proper operation of
construction businesses. The continued lack of capital is manifested by low
profits, risky bidding situations (underbidding), less investments into plants
and equipment, fewer new employment opportunities, and so on. Contractors have
seen the reduction of earned profits (based on sales or revenues) from
approximately 6% in 1972 to less than 3% in 1986 and even lower in 1991 (1).
A
major factor contributing to the increasing number of construction contractors'
business failures over the past few years is the shrinking profit margin. Dunn
and Bradstreet data (2) indicates major reasons for failure. It was noted that
more than 50% of the construction business failures were attributed to
"economic factors causes" in most of the years during the
1984-1989 period. There is no reason for the trend to be otherwise during
the 90s decade. "Economic factors causes" include insufficient
profits, lack of capital and high interest rates, among others. The retainage
policy, presently by owners, both public and private, contributes significantly
to the increase of "economic factors" in causing business failures in
construction.
Text
and reference books on the subject do not clearly explain the rationale behind
retainage, and in particular the selection of the 10 percent figure. Over the
years, the construction industry seems to have complacently accepted the idea of
the 10 percent retainage as being the norm. Many years ago, it was normal to
retain as much as 15°/a (3). Until the end of the 1960s decade, contractors
were still having a positive cash flow even after the 10 percent retainage was
deducted from their progress payments. The amount of 10 percent retained had
little economic effect on the contractor other than deferring a portion of the
profits. Under the prevailing economic situations in the industry perhaps the
practice of 10 percent norm is not realistic anymore. Dunn and Bradstreet data
indicates that availability of cash or lack thereof determines business
survival. It should be recognized, however, that retainage alone does not cause
all the cash flow problems. Lack of sound management policies, poor
business/accounting practices, and absence of effective quality control measures
are the main reasons that cause business failures and cash flow problems in the
construction industry.
Recognizing
the importance of the problem, the State of Florida through the Building
Construction Industry Advisory Committee (B.C.I.A.C.) funded a research project
to investigate viable alternatives to the standard 10 percent retainage
practice. The project was undertaken to study the concept of retainage with a
view to comprehend its intended purpose and to identify alternatives from the
perspectives of the industry professionals. This paper presents significant
findings of the investigation.
The
issue of retainage, as practiced in public construction, is discussed in this
paper from the perspectives of different groups that make up the construction
industry. Opinions and ratings of two main groups, the public agencies and the
general contractors, on the basis of the findings of a questionnaire survey, are
presented in this paper. The survey was conducted in the state of Florida
through the mail. The paper presents alternatives that are in use by some
agencies and alternatives that are suggested by experienced individuals. Further
work must be done before the industry, as a whole, can reach a consensus and
adopt alternate methods of retainage. This paper would be useful to those in the
construction industry who are responsible for and authorized to initiate and
introduce changes for the betterment of the industry.
Background
of the retainage policies, specifications related to retainage, and variations
practiced by different public agencies are covered in the following section.
Next, the approach used to conduct the research project, the design and
development of the questionnaire survey, are described. In the
"findings" section, we present the significant results obtained from
the survey. Opinions and ratings of two diverse groups, the public agencies and
the general contractors, on the effects of current retainage practice and
variations are contrasted and compared. In the last section, conclusions and
recommendations based on the study results are outlined.
Retainage
consists of holding back a stated percentage (usually 10%) from each progress
payment to be paid upon completion of either the contractor's work or completion
of the entire project.
The
rate of retainage is generally set forth in the Contract rather than the General
Conditions. Clough (4) write, "A retainage of 10 percent for the entire
project has been typical, although reduced percentages and other retainage
arrangements are now the rule. In any event, retainage on larger projects
results in the owner having custody of large sums of the contractor's funds for
extensive periods of time."
Where
performance and payment bonds are required, the withholding of retainage seems
to be duplicative protection to the owner. However, this added protection is
easier for the owners to access than bond security. Owners regard retainage as
an additional inducement for the contractor to maintain orderly progress of the
work. Clough (4) continues,
"...retainage
does have some undesirable aspects for owners, general contractors, and
subcontractors alike. Subcontractors are involved because general
contractors normally apply retainage to their subcontractors in the same
percentage as the owner applies it to the general contractor. Retainage
can and does produce real cash flow problems for the contractor, resulting
in substantial borrowing at hefty interest rates. This results in higher
construction costs for owners. In addition, it discourages contractors
from bidding some projects, thus reducing competition. Withholding
retainage from a subcontractor until completion of a project, even though
its work may have been satisfactorily completed long ago, is particularly
unfair. Yet the general contractor cannot be expected to remedy this
situation from its own funds." |
To
reduce the undesirable effects of retainage, a number of changes have been
introduced in recent years. Although not commonly used, these alternatives,
mentioned in Clough (4) have been used to develop the questionnaire survey for
the research project. Some of these are:
·
10
percent retainage is withheld only during the first half of the project, with
subsequent progress payments made in full. An alternative to this is to apply 5
percent retainage to the entire project.
·
Another
variation of the above alternative is, as the project passes the 50% completion
point, the normal rate of retainage of 10 percent can be reduced to 5 percent
for subsequent payments.
·
A more
recent development is where 10 percent is retained on each work category (or
work package) of the project until that category is 50 percent completed, after
which full payment is made if the work of that category is proceeding
satisfactorily.
·
On some
public projects, 10 percent is withheld for the entire project but the
contracting officer may authorize full payment when satisfactory progress is
being achieved. The federal government has discontinued the routine use of
retainage on direct federal construction that is on or ahead of schedule and
otherwise substantially in compliance with contract requirements.
·
Substitution
of certificates of deposit or interest-bearing securities for retention
holdback. Securities, whose value is equal to the required retainage, are
provided in escrow to the agency by the contractor with all interest earned
being paid to the contractor. A recent amendment of Florida Statue Chapter 713
section 255.05 has been passed to allow substitution of cash retainage with
approved securities.
Specifications Regarding
Retainage
Perhaps
the most widely used documents in construction contracting are those published
by the American Institute of Architects (A.I.A.). Specifically, the A.I.A.
document A201 (5), that has been, in general, approved and endorsed by the
Associated General Contractors (A.G.C.) of America, is the document that is
considered the keystone document coordinating the many parties involved in the
construction process. Article 9 of the A.I.A. document A201 establishes the
guidelines by which payments to the contractors are to be processed. This
article allows the owner to retain a portion of the payments due to the
contractors, basically until final completion. Although this document does not
establish the percentage to be retained, the 10 percent figure is the one most
widely used in the industry. The A201 document, however, does require the
contractor to obtain a consent from the Surety before requesting any releases or
reduction of retained amount.
The
A.I.A. document also requires that the contractor pay promptly each
subcontractor upon receipt of payment from the owner, but it also allows the
contractor to retain a portion of the payment from the subcontractors. Again,
the retainage amount is not stipulated, but it is customary to withhold the same
amount the owner retains from the contractor, usually 10 percent. A.I.A.
document states that payments to suppliers and subcontractors will reflect the
percentage actually retained from the upper tier contractor.
Associated
General Contractors (A.G.C.) of America supports the policy of 5% retainage
throughout the project except when the owners retainage is greater than 5%, in
which case the higher amount would govern, and provided that the security
between the G.C./Subcontractor is the same as that between the G.C./Owner.
In
the public sector, most public agencies have developed their own terms and
conditions of the contract, which somewhat follows the intent and the basic
structure of the A.I.A. A201 document, with their own specific clauses for
retainage. They vary from agency to agency. But they all basically require the
owner to retain a certain portion from payments due to contractors.
Recent
Changes in Retainage Policies of Public Agencies
Most
public agencies, including the Federal Government General Services
Administration (G.S.A.), have revised traditional retainage policy. The prior
standard of 10 percent throughout has been reduced. Many public jobs require
only5percent. The Department of Defense (D.O.D.) and G. S. A. have adopted the
policy that retainage should be withheld only for specific reasons such as
failure to maintain schedule. They experimented with the elimination of
retainage provisions and have found that bids for work have come in at
comparatively lower prices than in those situations where the general contractor
has imposed retainage provisions on subcontractors (3). On most federal
government projects the specific agency issuing the prime contract will normally
determine the amount of retainage to be withheld. The amount varies from the
current D.O.D. "policy" of zero retainage if the project is proceeding
satisfactory (10 percent retainage if the contracting officer believes there is
any problem with the progress or performance) to the old federal government
standard of 10 percent retainage up to 50 percent completion, with zero
thereafter if performance is satisfactory.
The
underlying principle of the G.S.A. policy is that retainage should not be used
as a substitute for good contract management, and contracting officers should
not withhold funds without cause. G.S.A. form 3506 (Rev. 10‑90) states:
"If
the Contracting Officer finds that satisfactory progress was achieved during any
period for which a progress payment is to be made, the Contracting Officer shall
authorize payment to be made in full. However, if satisfactory progress has not
been made, the Contracting Officer may a maximum of 10 percent of the amount of
the payment until satisfactory progress is achieved. When the work is
substantially complete, the Contracting Officer may retain from previously
withheld funds and future progress payments that amount the Contracting Officer
considers adequate for protection of the Government and shall release to the
Contractor all the remaining withheld funds. Also, on completion and acceptance
of each separate building, public work, or other division of the contract, for
which the price is stated separately in the contract, payment shall be made for
the completed work without withholding of a percentage."
In
the following, current retainage practices of Florida Department of
Transportation (D.O.T.) and Hillsborough county in the state of Florida are
described.
Florida
D.O.T.: "The
retainage policy of the Florida Department of Transportation for many years was
10% of monies earned until 50% of the contract was complete‑then 5% until
90% was complete; then 2-1/2% until final acceptance; then, if no problems
were ongoing (no disputed claims, etc.) the Department might hold only a nominal
retainage (1/2%) while the final review of quantities and other paperwork is
being finalized prior to final payment. The F.D.O.T. now allows contractors to
substitute securities for retainage. and thereby obtain the release of retainage
monies and earn interest on the securities.
Hillsborough
County: Hillsborough
County's construction contracts currently require 10% retainage until 50% of the
project is complete. The contractor may then request that no more retainage be
withheld. If the Project Manager feels that the progress of the job and quality
of work is acceptable at that point, no additional retainage will be withheld,
unless the progress of the work or the quality of the work deteriorates to the
point that the Project Manager feels that additional retainage is required.
Purpose and Effects of
Retainage
An
individual's position within the industry will probably determine his/her
opinion relative to advantages and/or disadvantages of retainage. In the
following, major concerns of the owners, general contractors, subcontractors,
bonding companies and lending institutions, as related to the issue of retainage
are outlined.
Owners:
Owners,
both public and private, tend to believe that there is absolutely no way to get
all the necessary work items completed with holding retainage. They are
concerned that contractors might walk off the job before completion if no
retainage is held or if retainage amount comes close to cost of work to complete
project. Owners do not see without retainage, how contractors can be held
responsible for items, such as: work not done, poor work that must be corrected,
code compliance, delivery of warranties, guarantees, operating instructions,
parts information, compliance with mechanics lien law, occupancy and other
permits, inspection reports, as-built drawings, etc. Owners do not think
that bonds can be effectively utilized to address these concerns.
General
Contractors: General
Contractors, in general, feel that 10 percent retainage amount is
unrealistically high and by holding this amount owners are actually forcing them
to finance part of the project. Contractors feel that owners should not be
earning interest on retainage. Their major concern is that it hurts their cash
flow. They tend to think that owners are being doubly protected, by bonds and by
retainage. Contractors also worry that owners would use (or abuse) the retainage
fund against backcharges.
Subcontractors:
It
appears that subcontractors are more adversely affected due to retainage than
the contractors. This may be caused by the use of
"pay-when-paid" clauses in contracts between contractors
and subcontractors. Although most contracts call for "timely" payment
to subcontractors by the constructors, the interpretation of the term
"timely" is most often subject to disagreement between the contracting
entities. The existence of the retainage practice is a cost factor to the
subcontractor. If the subcontract provides that the retainage be withheld until
completion of the entire project, it is especially unfair to such subcontractors
as the excavator and steel erector whose work is completed early in the course
of construction. Such a provision create very severe hardships on
subcontractors.
Bonding/Surety
Companies and Lending Institutions: The issue affects the decisions of credit evaluators
(bonding and lending institutions) in several ways. They want timely completion
of projects according to specifications. On the other hand, they also desire
that contractors, subcontractors and suppliers are able to maintain smooth cash
flow. Bonding companies get concerned if they see that the retained amount is
too high since it increases the likelihood of contractor-failures. In the
event of a failure, however, they would like to get hold of the retainage fund
for completing the job. Lending institutions' (banks) concerns are similar. They
want smooth cash flow of the contractors/ builders since it ensures repayment of
the loan. They try to avoid delay in project completion since it will also delay
the process of income-generation of their clients. The higher the
percentage of retainage, the more closely these financial institutions (bonding
and lending) need to check out the credit worthiness of the customer and the
project. On the other hand, with a lower rate of retainage they must monitor the
progress of the project and must verify that the subs and the suppliers are
being paid regularly.
Banks
and bonding companies frequently face another retainage-related issue, and
that is, how to treat unpaid retainage when reviewing contractors' financial
statements (3). Some do not count retainage as a receivable until the contract
is complete. Others record retainage as a current asset throughout an entire
project. Thus one needs to know the accounting basis used by a contractor before
evaluating his statement. If the retainage is due and payable well in the future
and if there is a concern about the contractor's ability to pay promptly in case
the owner delays payment, then unpaid retainage cannot be considered as current
asset.
Questionnaire Survey
A
questionnaire survey was conducted as one of the main approaches of the research
project. It was mailed out to different segments of the construction industry
throughout the state of Florida.
In
October 1991, 808 questionnaires surveys were mailed out to different groups
involved in the construction business in the state of Florida. Florida Builders
and Contractors Directory 1991(6) was used to generate the survey mailing list.
A cover letter was included with each survey. The objective of the research
project and the importance of the response were emphasized in the letter. A
"no‑postage necessary" return envelope was included with each
questionnaire survey. In most of the items readers were asked to respond either
by a check mark or a number from a predefined scale.
General
Contractors, architects/engineers, subcontractors, developer/builders,
design/build firms, and some selected public agencies in the state of Florida
were included in the survey. For a complete and detailed description of the
research procedure and results, interested readers are referred to (7). Specific
questions on how the respondents feel about the existing 10 percent retainage
practice, how they think that the policy affects the industry and finally how
they rate some of the alternatives, as listed in the questionnaire, were asked.
In this paper responses obtained from two diverse groups, the public agencies
and the general contractors, are presented.
In
the general contractors' group, 55 responses were received out of 260 mailed,
with a response rate of 21 % and from the public agencies, 38 responses were
received out of 68 mailed with a responses percentage of 55.9%.
Findings
General
A
majority of the general contractor (GC) respondents indicated that in 76% to
100% of their work they experience 10 percent retainage throughout the project
duration. It can be concluded that although there are other methods of retainage
in practice, they are not as widely used as the standard 10 percent method.
Respondents
were asked to write in any other method they encountered. Following methods were
mentioned.
·
10% until
substantial completion than 5%.
·
10% till
50% completion then 5% on balance.
·
0-75%
no retainage, 75-100% 10 percent of value of
·
uncompleted
work exceeding 75% of contract amount.
·
5% flat
retainage.
Most
of the general contractors retain from their subcontractors using 10 percent
flat procedure. They follow this procedure regardless of the method used applied
on them by their clients/owners.
The
cost of financing the retainage amount is never added to the bid price by most
of the GC respondents. A majority
(70%) of the GC's feel that there are other measures that serve the same purpose
as the 10 percent retainage. Only 25% of the public agency respondents agree
that retainage is a duplicative measure that protects the owners.
Major Effects of 10 Percent
Retainage
Opinions
on the effects of the 10% retainage, as it is practiced, were sought from the
participants. As predicted, responses are heavily influenced by the responding
individual's nature of involvement in the construction industry, or in other
words, by the group he or she belongs to. Table 1 shows the responses obtained
on the seven major effects from the public agency and the general contractor
respondents. These results are expressed in terms of percentage. The percent of
respondents who indicated either "agreement" or "strong
agreement" are combined and shown in the table along with the total number
of respondents. In addition to these two responses participants were allowed to
check "disagree," "strongly disagree" and "do not
know/no opinion".
A
considerable number of GC's agree with the statement that 10 percent retainage
cuts into already marginal profit. 60% of public agency owners disagree or
strongly disagree with the statement.
GC's
overwhelmingly believe that they are forced to finance the retainage amount. 31
% of public agency owners indicated either agreement or strong agreement and 41
% of them indicated disagreement or strong disagreement.
Majority
of the responding general contractors (54%), either agree or strongly agree with
the statement that retainage prevents contractors from investment opportunities.
22% of public agency owners agree or strongly agree and 50% disagree or strongly
disagree with this statement.
Most
of the respondents in the two groups agree to some extent that due to retainage,
contractors front‑load construction projects. About 20% in each group
disagree.
87%
of the responding public agency owners either agree or strongly agree that
owners are protected by the use of 10 percent retainage policy. 65% of general
contractors either disagree or strongly disagree with the statement.
A
majority of the respondents did not any correlation between contractor
bankruptcies and retainage. Most of those who indicated agreement or strong
agreement are the general contractors (32%).
59%
of the responding GC's think that relationship among the various groups in
construction will improve (indicates that they agree or strongly agree). 82% of
the public agency owners think that it will not (indicated by disagreement or
strong disagreement).
Alternatives to Standard
10% Retainage Practice
Responses
on the six enlisted alternatives are summarized in Table 2. These alternatives
were complied from literature on construction contracts and from the input of
experienced individuals. In addition, respondents were also encouraged to
suggest other alternative(s). Respondents were asked to use a predefined scale
(poor to excellent) to grade the stated alternatives. Numbers given in Table 2
represent the percentage of respondents that rated the stated alternatives as
either "good", "very good" or "excellent".
The
alternative that received the highest score (85%) from the GC's is "deposit
retainage to an interest bearing account." This was also the most favored
alternative by the public agency respondents (47%). Responses obtained on this
alternative indicate that most people feel it is fair to pay interest on
retainage to the contractors.
The
second most favored alternative by the GC's (83%) is "retain 10% until 50%
complete and none thereafter". 33% of the public agency respondents also
favored this opinion. As mentioned earlier, this alternative , or some kind of
variations, are being used by many agencies.
General
contractors and public agency respondents differed widely on the alternative
"reduce retainage to 5% or other realistic rate." 73% of the GC's v.s..
only 19% of the public agency respondents thought it was an acceptable
alternative.
Similar
responses were indicated to the alternative, "Eliminate retainage, protect
owners by bonding only." 11 % of the public agency respondents v.s.. 61% of
the GC's respondents favored this alternative. It is interesting to note the
"No change is necessary" received favorable response from 72% of the
public agency respondents and only 20% of the responding GC's.
Other Alternatives
Suggested by the Respondents
Respondents
were asked to suggest other alternatives that were not listed in the
questionnaire. Following is a summary of the suggestions made by the respondents
of the survey.
"Maintain
10% retainage, get waivers for materials and subcontractors work."
"10%
until 50% complete if work is on schedule and satisfactory-reduce to 5%
with opinion to increase back to 10% if work falls behind schedule."
"The
owner holding and releasing 10% of each subcontractor's contract directly to the
subcontractor upon ok from contractor."
"Securities
of deposit placed on large or extended term projects with a public agency."
"Owners
hold actual retainage amounts for unsatisfactory or incomplete work, and release
it when work is corrected or completed.
"If
the bonding companies would be easier to work with, then the 10% retainage will
become unnecessary."
"Write
retainage procedure appropriate for the particular project, I favor 10%
retainage throughout most of the project with the percentage going down at the
end."
"Allow
the retainage expense to be a bid item along with insurance, bonds, etc."
"Force
GC's to use same method with subs as they receive from the owner e.g., if GC's
receive interest they should pay interest to subs on retainage."
"Use
a sliding scale, but never reduce to 0% till the final payment. Percentage to
vary based on size and nature of project."
Summary and Conclusions
The
research project, partial results of which are reported in this paper, was
undertaken to investigate the practice of retainage as one of the factors that
might be contributing to the contractors' lack of profit and difficult cash flow
situation. It was considered by the Building Construction Industry Advisory
Committee (B.C.I.A.C.) of the state of Florida- as manifested through
funding of this project as one of the areas that should be looked into for
possible modification by the industry participants. Although retainage is not
the only factor that causes cash flow problems in the construction industry, it
might be one of the most significant factors affecting project cost and cash
flow.
Most
of the respondents to our study cited 10 percent retainage as a factor that
contributes to the general contractors' and the subcontractors' cash flow
problem. General contractors and subcontractors think that it is a major problem
and the practice should be fundamentally revised. Many felt that it is the
subcontractors who eventually carry the burden of retainage; contractors almost
always manage to pass-on this burden to the subs. Most contractors retain
10 percent from their subs regardless of the methods used on the GC's by the
owners. A majority of public agency respondents to our survey see retainage as a
very effective and practical tool for owners' protection; especially to have the
punch list items done and the close-out documents handed over.
Most
owners use retainage as a protection against unwilling contractors to finish the
work. Bonding is not considered as a practical solution to this problem.
Enforcement of bonding is a time-consuming and difficult process, most
owners would like to avoid. It is unusual to use bonds for finishing punch list
items. Obviously, most contractors feel that the owner is being doubly
protected, first by bonds and then by retainage. Bonding, however, has direct
consequences on the practice of retainage. It is generally believed that bonding
price would go up and would become even more difficult to obtain if there were
no retainage.
It
was found that many government agencies are practicing variations of the flat 10
percent retainage, despite the fact that most of the public agency respondents
are not in favor of revising the traditional retainage practice. Many public
projects require only 5 percent, and some federal agencies have adopted the
policy that retainage should be withheld only for specific reasons such as
failure to maintain schedule.
Decreasing
the rate of retainage as the project progresses satisfactorily towards
completion was suggested. Periodic release of retainage based on trades or work
subdivisions was mentioned as an alternative. Payment of interest on retained
money to contractors and subcontractors was favored by many as a fair provision.
Timely full subcontractors payment, as their work completes, was suggested to
alleviate the problems caused by retainage. Many in the industry think it is
reasonable to retain lower percentage for larger jobs.
Middle
grounds, somewhere in between the flat 10 percent retainage and total of
retainage from contract clauses, seem to be favored by most of the respondents.
It was expressed by many respondents and interviewees that the retainage policy
should be revised so that it does not create excessive pressure on the
contractors and subcontractors but at the same time it should also be available
to the owner as a tool for protection against irresponsible contractors.
Acknowledgments
The
research work presented in this paper was sponsored by the Building Construction
Industry Advisory Committee (B.C.I.A.C.) under a grant from the state ofF7orida,
Department of Education. The authors are grateful to B.C.I.A.C. for sponsoring
this project.
References
1.
Adrian, J.J. (1987). Construction Productivity Improvement, Elsevier,
New York, NY.
2.
"Business Failure Record," (1894-1990). The Dunn and
Bradstreet Corporation, New York, NY.
3.
Cushman, R.F. and Bigda, J.P. (1985). Construction Business Handbook,
2nd ed., McGraw-Hill, New York, NY.
4.
Clough R.H (1985). Construction Contracting. 5th ed., John Wiley &
Sons, New York, NY.
5.
"General
Conditions of the Contract for Construction," (1987) AIA Document A201, The
American Institute of Architects, New York, NY.
6.
Florida Builders and Contractors and Directory, (1991). The Builders
Book, Ft. Lauderdale, Florida.
7.
Ahmad,
I and Barnes, W.C. (1992). Alternatives to 10% Retainage, Technical Publication
No. 107, Dept. of Construction Management, Florida International University,
Miami, Florida.
Table
1. Public Agency (P.A.) and General Contractor (G.C.)
Ratings
of the Effects of Retainage
Effects
of Retainage |
P.A./G.C. |
Total No.
of Respondents |
Agree or strongly
agree |
Cuts
into contractor profit |
P.A. |
32 |
19% |
|
G.C. |
54 |
88% |
Forces
contractor to finance |
P.A. |
32 |
31
% |
retainage |
G.C. |
54 |
72% |
Prevent
contractors from |
P.A. |
32 |
22% |
investment
opportunities |
G.C. |
52 |
54% |
Contractor
front-load |
P.A. |
38 |
63% |
due
to retainage |
G.C. |
54 |
67% |
Ten
percent retainage |
P.A. |
38 |
87% |
protects
owners |
G.C. |
55 |
27% |
Contractor
bankruptcy will decrease |
P.A. |
38 |
11
% |
if
retainage is removed or revised |
G.C. |
54 |
32% |
GC.
A/E and owners will have
improved |
P.A. |
38 |
8% |
l
relationship If retainage is revised |
G.C. |
54
|
59% |
Table
2. Public Agency (P.A.) and General Contractor (G.C.)
Ratings
of the Alternatives to 10 Percent Retainage
Alternatives
to 10 Percent Retainage |
P.A./G.C. |
Total No. of Respondents |
Rated good, v.
good or |
No
change is necessary |
P.A. |
36 |
72% |
|
G.C. |
51 |
20% |
Deposit
retainage to an interest- |
P.A. |
36 |
47% |
bearing
escrow account |
G.C. |
53 |
85% |
Reduce
retainage to 5 % or |
P.A. |
36 |
19% |
other
realistic figure |
G.
C. |
52 |
73% |
Retain
10% until 5096 completion |
P.A. |
36 |
33% |
and
none thereafter. |
G.C. |
53 |
83% |
For
jobs 1 yr or longer |
P.A. |
36 |
34% |
release
retainage periodically |
G.C. |
52 |
44% |
Eliminate
retainage, protect |
P.A. |
37 |
1
% |
owner
by bonding only |
G.C. |
54 |
-61
% |