(pressing HOME will start a new search)
|
|
THE
PLANNED USE OF THE CONSTRUCTION SITE AND ITS IMPACT ON PRODUCTIVITY AND COST
|
The
construction industry lags behind other industries in planning the use
of its physical plant, the jobsite. This insufficient planning increases
the cost to store and handle material, as well as the cost of
production. Eight materials handling principles are defined, and the
impact of violating these principles on construction productivity and
cost is explained. procedure for
planning the use of the jobsite is outlined. KEY WORDS: Construction,
planning, site, storage, handling, material, production, cost |
INTRODUCTION
Cost
and production control in the construction industry is an on-going concern for
most construction managers. Frequently, their efforts are reactionary rather
than pro-actionary. They react to an activity after it is apparent that it will
be over budget, rather than "pre-building" the job so that few
surprises are encountered. The planning effort becomes key to controlling the
cost of the project. One phase of the planning function, the use of the
construction site, will be discussed in this paper. Topics include current
industry practices, educational opportunities available, and the principles and
procedures for developing the site plan.
MATERIAL HANDLING AND SITE UTILIZATION IN THE CONSTRUCTION INDUSTRY
Current Practice
Limited
research suggests that materials handling principles and site planning
techniques are either not being applied, or are being applied ineffectively in
the construction industry. A time-lapse study by Burkhart and Pault of Phelps,
Inc.(1983) indicated that the carpenters spent approximately 40 percent of their
time waiting for materials. The activity photographed and analyzed was a simple
column forming operation on a commercial structure. The authors concluded that
one of the key problems was that materials were not stored close enough to the
work area.
A
series of 22 productivity studies carried out by O'Brien (1989) found that
electrical workers spent only 32% of their day on fully productive activities.
Site workmen spent 42% of their time on get-ready types of activities such as
material handling and set-up operations.
As
part of a study by Thomas, Sanvido, and Sanders, the erection of steel for a
five-story building was interrupted by a lack of materials. When materials were
made available, production was slowed because of poor site storage practices and
no planned use of the site. The results of the study indicated that work-hour
overrun was 18 per cent. This figure is three-times the overrun estimated by the
Construction Industry Institute for industrial projects. In addition, by
comparing this project to a well-run project, the researchers calculated that an
investment of $ 1,570 in planning this activity would saved $8 ,942 in
quantifiable disruptions, a benefit/cost ratio of 5.7 to 1.
Current Education
A
review of recent college catalogs (Muehlhausen, 1988) of 13 accredited schools
of the Associated Schools of Construction (ASC) indicated that planning the use
of the construction site to facilitate handling, storage, and erection of
materials in a timely and cost-effective manner was, at best, a hidden part of
the curriculum. The planning courses that were offered in the curriculum
appeared to emphasize the students ability to design, schedule, and budget the
project. Materials related courses emphasized materials properties and use for
designing and building the structure. Methods courses tended to stress the type
of building system and the resultant labor and equipment needed to erect the
materials for the given system. Apparently, the principles and procedures for
planning the use of the construction site was not a part of the classroom
experience.
A
review of a few construction management methods textbooks (Adrian, 1981;
Anderson & Woodhead, 1981; Barrie & Paulson, 1984; Clough & Sears,
1979; Drewin, 1982, Fisk, 1984; Halpin & Woodhead, 1980; Kimmons, 1990;
Lion, 1980; Maher, 1982; McNulty, 1982; Nunnally, 1980; Parker & Oglesby,
1972; Puerifoy & Ledbetter, 1985; Wood, 1977) indicated that construction
site utilization was not a priority concern. For example, the formulation of a
plan for the storage, fabrication, and movement of materials on the
construction' site was presented in two paragraphs in Peurifoy and Ledbetter
(1985). A more recent work (Kimmons, 1990) spends one chapter on materials
management activities. However, the planned use of the construction site is not
included. Material handling and storage and the efficient use of the jobsite was
not a priority concern.
Chandler
(1978) did offer the rudiments of a systematic approach to materials management
in the construction industry. However, the book, which was published in Great
Britain, was not readily available for distribution. (T. Fry, personal
communication, January 22, 1985.) In an effort to provide information to
construction managers who wanted to establish materials management systems on
their projects, the Construction Industry Institute (1987) prepared a project
materials management handbook. The contents described the ingredients of a
materials management system for the industrial sector of the construction
industry. The section entitled "Site Management" did devote
approximately one page to warehousing and lay down areas, but failed to describe
the principles and procedures for developing the site plan.
In
summary, it appears that construction curricula do not offer learning
experiences to the student to plan the use of the construction site. The
"planning" effort seems to stop with the job schedule and the job
budget. The schedule is the plan which identifies the timing and duration of a
work activity, which identifies the construction resources needed at their point
of use on the site. The budget is the plan which identifies the amount and
timing of the cost of these resources.
The
intelligent, planned use of the site will
minimize loss in production, and will minimize increases in cost due to
double handling, moving materials over long distances, improperly handling and
storing material, construction delays, congested work areas, and a host of other
jobsite related problems which keep construction materials from flowing smoothly
to the cratsmen when he needs them. The site plan becomes a key element to
complete the project on time and within budget. Yet, construction curricula
apparently expresses little concern for this area of construction management.
PLANNING MATERIAL FLOW
Planning Yields Profit
A
common single leading reason for marginal or no profit on construction projects
is insufficient planning of construction activities. From the contractor's point
of view, it is the first management activity which influences material flow and
is probably the most critical. A detailed plan where the planning team virtually
"pre-builds the project" is the most effective way to minimize site
material handling and storage costs, and minimize delays due to lack of
materials at their point of use when needed.
Many
contractors think that once the job budget (plan of the cost of resources) and
project schedule (plan of the sequencing and timing of the use of resources) are
completed, the initial project planning is completed. However, these two pans
are actually peripheral to the physical acts of constructing the project. They
do not identify the method by which an activity will
be accomplished, the resources required to accomplish that activity, or the
use of the construction site so that activities are accomplished without
constraint.
O'Brien
(1989) states ".. very little preplanning [is done] by contractors,
especially in the area of materials handling... There is too often a `project
slump' period between popping the champagne corks to celebrate the successful
bid and actually starting work on the site. The high level of activity build-up
during the estimate preparation drops off drastically [after the award of the
contract]." The difference between success and failure is dependent upon
how the contractor uses this `slump time'. If the contractor prepares a
schedule, a budget, and material handling plan, then project profits will
be maximized.
Planning
does not come without a cost. The project management team must take the time to
plan a project in detail. This includes interacting on a detailed level with
subcontractors and suppliers. It takes time and costs money to plan! Does
spending big bucks on construction projects in the planning give a return on
investment?
Does
this overhead cost generate more profits in sufficient amount to justify the
cost? Consider the data found in Figure 1 based on the track record for general
contractors in the United States (Robert Moms Agency Annual Statement Studies,
1989):
![]() |
Figure
1. Required cost impact of planning. |
The
relationship between job costs and earnings from projects was about 85% for a
contractor whose earnings were $10,000,000 per year. This means that for every
one dollar earned by the company $ .85 was spent on labor, material, subs, job
overhead, or other job related cost. Overhead, those costs associated with being
in business (often referred to as company costs), was 13% of earnings. This cost
structure yielded profits of 2% of earnings.
Suppose
the general contractor spends that $ 200,000 of profit (on $10 million in
earnings) to give project management the time and resources to carefully plan
the job in detail. In order to breakeven, that is to return $200,000 or 2% of
earnings, the implementation of the plan must reduce job costs by 2.4%. Is this
possible? Limited studies indicate that it is! Thomas, Sanvido, and Sanders
quantified the cost to benefit ratio as 5.7 to 1, the Construction Industry
Institute arrived at a 2 to 1 ratio, while Proctor and Gamble found that
preplanning yielded a ratio of 4 to 1. These studies indicate that detailed
planning (especially for those contractors who do not currently plan in detail)
will probably save more than the 2.4% in job costs. If a 5% savings m lob costs
is realized, then profit increases 112%. If a 10% savings in job costs is
realized, then profit increases 325%. Obviously, the planning effort, even with
the associated costs involved, is worth it!
MATERIAL FLOW ALTERNATIVES
Most
construction materials arrive at the jobsite from an off-site point of origin.
Once at the construction site, there are three possible alternatives to
the flow of material: direct, indirect, and multiple indirect. These
alternatives and their impact on cost are graphically represented in Figure 2.
|
Figure
2. Material Flow Alternatives |
Material
will flow directly to its point of use when applying the direct material flow
alternative. In this instance, material handling and site storage costs will
be minimized. Double handling does not occur, site handling distances are
minimized, and storage of material on the site is of short duration. The direct
material flow alternative requires strict control of vendor delivery. An example
of the use of the direct material flow alternative for site planning was the
construction of an office building complex in Los Angeles by Olympia and York
Developers. The plan included finely-tuned delivery schedules (15 minute windows
on tower cranes), controlled movement of materials from a command center,
systematized storage, and special handling procedures such as oversized hoists,
a delivery truck turntable, and one-way drive-through lanes to speed deliveries
of materials to their point of use. Approximately 152,000 man-hours were saved
on this $92 million project.
When
using the indirect material flow alternative, materials are stored for a
short period of time on the construction site before being moved to their point
of use. This indirect flow of materials, is commonly practiced when material
deliveries cannot be closely controlled and
site
constraints do not allow the material to be stored at its point of use in
advance of need. Handling and storage costs will increase when using this
alternative. However, an effective plan avoids delays due to unavailable
material at its point of use, and the resultant high cost of labor. A balance is
struck between material handling and storage cost, and labor cost savings to
yield the lowest project cost.
Too
often there is no "planned use" of the site. Material arrives at the
site and is stored in any available space. The storage area is selected due to
convenience of unloading, with no regard to future use. Invariably, the location
chosen interferes with construction progress, requiring material to be moved to
another storage location. Unnecessary additional handling and storage costs are
incurred when the multiple indirect flow alternative is used.
In
all material flow alternatives, it is interesting to note that "material
handling adds cost to the project but not value". If materials are handled
over long distances, are double handled, or are handled using an inefficient
method, then costs increase with no increase in the value of the project. The
ratio of material handling costs to total project costs will vary from 30-80%,
depending on the type of construction and the cost of the materials. It
is
apparent that a primary method of controlling project costs (even with a 30%
ratio) is to plan the use of the construction site and to minimize the material
handling and storage costs while making the materials available to the
craftworker when he needs them.
MATERIAL HANDLING OBJECTIVES
Materials
handling facilitates the flow of materials to their final resting place in the
project. If a brick layer is prepared to place masonry units in a wall, all
necessary materials must be at hand. If not, the bricklayer is idle, thereby
incurring cost with no production. Not only must there be brick and mortar
convenient to the mason's station on the wall, but there must be a scaffolding
system designed to aid the production process, not hinder it. In addition, a
fork lift is required to lift the masonry units and mortar onto the scaffold in
a safe manner.
Materials
handling is an integral part of the construction process and is of vital concern
to the contractor. The relationship between the materials handling function and
the production function is often transparent. While the visibility of the
materials handling effort is many times diminished by the production function,
it still exists as a definite identifiable entity.
The
objectives for planning, executing, and controlling the handling of material on
a construction site attempt to minimize the cost of construction. These
objectives include:
1.
Eliminate duplicate handling of materials. 2.
Minimize travel distance from material storage to material point of
use. 3.
Minimize site storage of materials. 4.
Provide a uniform flow of materials on the site, free of
interferences.
|
PRINCIPLES
OF MATERIALS HANDLING
All
construction sites vary. Each site exhibits characteristics which yield unique
material handling problems. When solving the material handling problems for a
given construction project, the contractor should apply the following generally
accepted principles:
1.
Move over shortest distance.
In
general, short moves require less time and cost less money than long moves. This
principle applies to transporting materials several miles on a highway project,
transporting materials from site storage to the structure, or moving materials
within the structure.
2.
Keep terminal time short.
The
object of materials handling is to move materials. Therefore, it is inefficient
to have material handling equipment delayed at terminals for pick-up or delivery
purposes. A scraper entering a cut should not have to wait on another scraper or
spend too much time loading. The delay, for whatever reason, increases cycle
time, decreases production, and increases the cost of production.
3.
Avoid partial loads.
E
Some hand trucks handle loads of 200 pounds; some ickup trucks handle 2000
pounds; some larger trucks andle 20,000 pounds. The cost of operating the hand
truck, pickup, or large truck is about the same whether they carry the full load
they are designed for or only a partial load. Thus, it is often a waste of money
not to use equipment to its capacity.
4.
Avoid manual handling.
Advancing
technology has created machines to perform tasks once performed by labor. In
general, it is uneconomical to handle material manually. Labor costs have
steadily risen, thus making manual handling increasingly more expensive.
5.
Limit the number of moves.
The
handling of material adds cost but not value to the project. If possible, move
material directly to its point of use. If not, have a detailed storage plan to
reduce material movement from one storage location to another.
6.
Use gravity.
Gravity
is the cheapest source of power known. It should be used whenever possible for
moving material. For example, a haul road should be located such that a loaded
vehicle operates down hill. If moving material from one floor to the next, the
laborers should carry material down stairs rather than up the stairs, . Concrete
is direct deposited through a chute more quickly and economically than any other
way.
7.
Bundle materials in like or complimentary units. (Unit-load principle!)
Materials
should be grouped together in a large and consistent size, or should be packed
in sets. The unit load principle facilitates mechanical handling of the
material. It also assures that all parts in an assembly are available when the
crafts worker needs them.
8.
Clearly mark materials.
All
materials should be clearly marked as to what they are and where they go.
Identifying the material or material packaging will promote efficient handling,
storage and retrieval of the material.
IMPACT OF MATERIAL HANDLING VIOLATIONS ON PRODUCTIVITY AND COST
Cost Per Unit
The
availability of space on the construction site may limit the alternative methods
to handle materials. Once the material handling method is selected, the site
must allocate space for haul roads and storage areas. This includes labor and
equipment used to handle the material. Two objectives dominate the construction
process:
The
method selected to handle a given material on site is generally the one which
minimizes the cost to build the project, or the time it takes to build the
project. The choice is dependent upon which material handling constraint (time,
space, cost, plant and labor) the project is operating under.
Generally,
the method chosen to handle a given material is the one which yields the lowest
cost per unit handled. This is true as long as the method does not negatively
impact future activities to complete the project. For example: Assume two
methods are available to excavate a basement, a hydraulic excavator with a hoe
bucket and a loader. Suppose the loader could excavate the basement at a lower
cost per unit, but is not as accurate and causes more hand excavation and loss
of concrete during the footing placement activity. It is possible that the
savings gained by using the loader was lost, and even more likely that
additional costs occurred due to the higher cost of installing the footings. At
all times, material handling decisions should be based on the impact on total
job costs and not on individual activity costs.
The
cost per unit is easily described mathematically as follows:
COST/UNIT
= RESOURCE
COST (dollars/hour)
METHOD
PRODUCTION RATE (units/hour)
WHERE:
Resource Cost is the cost of labor and equipment to handle the material for a given amount of time
Method Production Rate is the rate of production or the number of units handled over a given amount of time.
The
production rate can be mathematically expressed as follows:
RATE
= CAPACITY PER CYCLE
CYCLE
TIME
WHERE:
The Capacity is the number of units the chosen material handling method moves in one cycle. A material handling Cycle is the sequential and discrete elements to engage a load, move the load to a desired location, disengaged the load, and return for another load.
The
Cycle Time is the time it takes for the material handling method to complete one
cycle.
Impact of Violating Principles
When
the material handling principles are violated, one or more of the variables
which determine cost per unit will be affected. For example: For a given
material handling method, if the material is not moved over the shortest
distance possible on a project, then cycle time will increase. If cycle time
increases, rate of production decreases. If rate of production decreases, then
cost per unit increases.
Note
that the relationship is linear. That means that a 10% reduction in cycle time
yields a 10% decrease in production rate and a 10% increase in cost per unit.
Many times the construction manager is fooled into thinking that an activity
cannot be substantially improved upon, to warrant the time and effort to fully
utilize the material handling principles. For example: A typical hydraulic
excavator with hoe bucket can cycle once every 30 seconds with a swing angle of
180 degrees. If the work is planned to position the trucks so the excavator only
swings 90 degrees or less, then cycle time can be reduced by 3 seconds of more.
Most construction managers say, `Big deal! What's 3 seconds!' The answer is
noting if the machine only cycles one time; however, the machine will cycle
hundreds of thousands of times. If the manager can save 3 seconds or reduce
cycle time 10% on each cycle, then he has cut costs by 10% on this activity. In
this example, the manager has he reduced construction costs and has reduced the
time to complete the activity by increasing the rate of production.
There
is nothing sacred or earth shattering about the material handling principles and
their use in planning individual activities or the use of the jobsite. What most
managers fail to realize is that poor planning affects all activities, not just
one. Thus, errors are compounded over and over again. That is why such huge cost
savings can be realized if a project is "pre-built" in detail during a
planning period before the work starts.
THE PROJECT PLANNING EFFORT
Many
construction managers assume that the bid estimate is a detailed estimate of
construction costs. This is rarely the case. The purpose of the bid estimate is
to set the cost parameters for the completion of a project. Overhead costs are
acquired during the bidding process, with no guarantee that the contractor will
be awarded the contract. Therefore, there is no guarantee that the contractor
will get a return on the invested overhead dollars spent during the estimating
process.
Rarely
in the commercial construction industry does the estimator "pre-build"
the job during the estimating process. It would take too much time and cost too
much money to complete. Instead, the estimator completes a quantity take-off of
the materials, and extends the quantities using unit prices to estimate the cost
for labor and equipment to install the material. This practice allows the
construction firm to bid jobs in a cost-effective manner. However, it provides
the project planner with little information (other than milestone costs) with
which to plan the job. For example: A bid estimate may call for 10,000 square
feet of contact area for concrete formwork to build a cast-in-place concrete
wall. The bid estimate will apply a cost per square foot for material, labor,
and equipment to complete the forming activity. But does it indicate to the
project planner the details of obtaining and erecting the formwork? Does it
indicate the type of formwork? If it does, does it indicate the pieces required
to build these forms (panels, walers, strongbacks, wedge bolts, ties, etc.) and
the quantities required? If the panels are "ganged", does the estimate
indicate the size and type of crane required to handle the materials on the
site? Remember that an oversized crane will
be a waste of money on crane rental, while an undersized crane will
cost labor dollars due to delays! Does it tell the planner the labor
requirements for the forming activity? The answer to these and other questions
related to the actual construction process is almost always -- NO!
THE PROCESS OF JOB LAYOUT
The
process of planning the use of the construction site is not a casual thing. It
takes time and thought to prepare a plan which:
1)
identifies the appropriate methods to handle material;
2)
identifies areas for movement and storage of materials;
3)
identifies storage and handling requirements so that material does not
become damaged, lost, or stolen;
4)
and at the same time, insures that materials are available to the
craftsman when he needs them;
5)
ALL at the lowest project cost.
Because
of the many hundreds of activities that can occur during the process of
construction, it is important that the manager follow a set planning routine. A
suggested planning routine is as follows:
Prepare
a schedule for the project. The schedule will identify the sequence and timing
of construction activities. Thus, the planner will be able to identify
when
materials, labor and equipment are needed on the jobsite. The planner will also
be able to identify concurrent activities and their related material storage and
movement requirements. From this information, the planner can plan for material
movement at different stages of project completion without violating material
handling principles.
·
Activities required to complete the project. - Materials required for
each activity. (detailed description and quantity)
·
Packaging requirements for each material. - Handling requirements for
each material. Storage requirements for each material.
·
Storage area for each material (configuration). - Dates of materials to
arrive at the site.
·
Duration of materials to remain in storage. - Method to handle the
material
3. -Haul road requirements for the handling method (method selected for a specific material)
CONCLUSION
Current
research indicated that project management is not doing an adequate job in
planning and controlling the use of the jobsite. Educational opportunities to
learn about the principles and procedures for planning the use of the jobsite
were apparently not readily available. A site plan which applies basic materials
handling principles will effectively increase production and reduce cost during
construction of the project. A set planning routine will allow the construction
manager to become proficient in preparing a plan which maximizes the chance that
materials will be available to the craftworker when it is needed, and in a
cost-effective manner.
REFERENCES
Adrian,
J.J. (1981). CM: The construction management approach. Reston, VA.:
Reston. M
Anderson, S.D., & Woodhead, R.W. (1981). Project manpower management.
New York: McGraw-Hill. Burkhart, A. & Pault, J., (1985, January). How
to prove productivity in forming operations. published manuscript. Chandler,
I.E. (1978). Materials management on building sites. Lancaster; New York:
Construction Press. Construction Industry Institute. (1987). Project
materials management handbook. Austin, TX: Bureau of Engineering Research,
The University of Texas at Austin. Clough,
R.H. & Sears, G.A. (1979). Construction project management. New York:
Wiley & Sons. Drewin,
F.J. (1982). Construction productivity. New York: Elsevier. Fisk,
E.R. (1984). Construction project administration (2nd ed.). New York:
Wiley & Sons. Halpin,
D.W., & Woodhead, R.W. (1980). Construction management. New York:
Wiley & Sons. Kimmons,
R.L. (1990) Project management basics: a step by step approach. New York:
Marcel Dekker. Lion,
E. (1980). A practical guide to building construction. Englewood Cliffs:
Prentice-Hall. Maher, R.P. ((1982). Introduction to construction
operations. New York: Wiley & Sons. McNulty,
A.P. (1982). Management of small construction projects. New York:
McGraw-Hill. Nunnally,
S.W. (1980). Construction management and methods. Englewood Cliffs:
Prentice-Hall. O'Brien, K (1989, September). Planning has merit.
Electrical Contractor, pp. 53-55. Parker,
H.W. & Oglesby, C.H. (1972). Methods improvement for construction
managers. New York: McGraw-Hill. Parvis,
F.R. & Bradley, M.J. (1983, April). The layout of temporary
construction facilities. Cost Engineering, pp. 19-25. Peurifoy,
R.L, & Ledbetter, W.B. Construction planning, equipment, and methods
(4th ed.). New York: Mcgraw-Hill. Robert
Morris Associates. (1989). Annual Statement Studies, p. 408. Thomas,
H.R., Sanvido, V.E., & Sanders, S.R. (1989, September). Journal of
Construction Engineering and Management, pp. 370-384. Wood,
S., Jr. (1977). Heavy Construction equipment and methods. Englewood
Cliffs: Prentice-Hall. |