|
Picking
Successful Projects By Using the PRISMTM Model
Flynn
L. Auchey Virginia
Polytechnic Institute & State University, USA |
Gloria
J. Auchey, PMP, President,
The Success Institute of America, Inc., USA |
This
paper describes a process for improving the success of picking better projects
to bid by using the Project Risk Identification, Selection, and Management model
(PRISMTM). PRISM l has been refined over the past two years by
working with several construction companies who have developed their own
customized versions of the model. It was designed to be used with projects where
there were high quality historical data available for the analysis; therefore,
it was able to use the traditional tools of risk management, such as Expected
Monetary Value, Utility Theory, Pair-wise Comparisons and Critical Risk Ranking
Matrix to help contractors develop an effective bid-no-bid decision. The use of
the PRISM l model begins with the contractor creating a custom set of
critical project selection questions relative to potential project risk and
opportunity, which are quantified as to the probability of occurrence and cost
impact if they do occur. The data generated are then plotted to determine
potential project profitability of one project relative to other possible
projects being considered, which, in turn, helps the contractor make the best
go/no go decisions prior to committing significant resources to create a
full-scale estimate and bid on the project with the highest profit potential.
Thus, PRISM 1’s contribution to the procurement process is the improved method
for not only qualifying but also quantifying the project risk and opportunity
information on one project as compared to those of another project. In addition,
the contractor uses the output from the qualitative questions to form the basis
for creating an effective prioritized list of risks and opportunities to be
mitigated and managed before signing the contract and also after the project is
underway. In this way, the model serves as a template to store quantitative as
well as qualitative data about each project; the historical database created
helps to reduce the number of unknown-unknowns for future projects. By using
PRISM l to reduce overall risk and enhancing project opportunities, construction
companies can increase profitability on present and future projects. Keywords:
Procurement
Management, Risk Management, Project Selection Methods, Improving Project
Profitability, Assessing Project Risk and Opportunity |
Introduction
Too
many contractors are still going out of business within five years of start-up.
Dun and Bradstreet records indicate that as many as 56% of the contractors that
started up in 1995 have now gone out of business. There are various reasons for
their demise; however, negative cash flow remains one of the prominent reasons
cited. Contractors are bidding too much work, work that is either not a good
match for their asset base, or work that is beyond their geographical or
technical ability to control properly. (Engineering)
Several
studies have shown that the cost of resources to prepare a complete hard-bid
estimate for a construction project runs between 1/4 and 1/2 percent of the cost
of the project. (Bajaj; De la Garza; Duffield) That means that if a contractor
has to bid four $1 million projects in order to go to contract on one, the
assets wasted on trying to procure the three unsuccessful projects could amount
to as much as $150,000 dollars. In short, the contractor invests approximately
$150,000 before (s)he is ever able to go to contract on the successfully bid
project. Therefore, it is extremely important for contractors to make quick,
accurate decisions regarding which projects to bid before committing the crucial
resources to obtain the contract.
The
construction industry encounters extremely high risk due to such factors as the
uniqueness of every project and the exposure to external elements. (Kim) The
majority of construction companies prepare cost estimates based on a traditional
single figure cost estimation approach. (Leung) Although the estimators often
consider risks, those risks are rarely reflected in the final estimate in a
formal, systematic way. (Dexter; Diekman; Duffield) The most common method for
protecting the company from potential risk is to add a contingency sum to the
estimate. However, this approach has a number of weaknesses, including:
·
· The
contingency figure is usually arbitrarily arrived at and may not be appropriate
for the proposed project;
·
·
Estimators have a tendency to double count risks;
·
· A
percentage addition still results in a single-figure prediction of estimated
final cost, implying a degree of certainty that may not be justified by the data
available;
·
· This
method assesses risk only as a negative variable and doesn’t consider any
positive potential (opportunity).
As
a result, the traditional single-figure approach can be inadequate, misleading
and cost inefficient. (Ranasinghe) Therefore, the construction industry requires
not only a different approach to managing the risks associated with project
procurement but also a tool which organizes and quantifies project selection
information and stores valuable project procurement knowledge for future
decision makers and construction managers. The PRISMTM Model (See
Figure 1) incorporates three components in its development (PRISM l, ll, lll)
and is intended to accomplish these goals.
|
|
Figure
1. The PRISMTM
MODEL |
The
development of PRISM l is discussed in detail in this paper; whereas, PRISM ll
and lll are discussed briefly primarily to generate creative discussion and
feedback regarding their development. PRISM 1 focuses on creating a customized
list of questions, which are quantified and ranked using Expected Monetary
Value, Utility Theory, Pair-wise Comparisons, and the Critical Risk Ranking
Matrix.
By
developing this specific list of project selection questions, the model
overcomes one of the greatest difficulties associated with project selection
models: customization to specific company operations. Indeed, this customization
is one of the model’s unique characteristics, for once the list has been
customized, it reflects specifically how good a match a project is to the
inherent abilities and assets of a company.
Further,
the model provides a systematic approach in the identification and assessment of
potential positive as well as negative risks; this, in turn, provides a
management tool to help project managers choose appropriate courses of action in
managing project selection and risk. In this way, critical knowledge can be
stored which is easy to access, analyze and use in future project selection.
Indeed, the PRISM 1 Model not only provides an innovative approach to project
risk analysis and procurement using tried and tested risk management tools but
also creates a template to give construction managers an at-a-glance
quantitative assessment of the project as compared to other possible projects.
The template developed is unique to the operations of the company for which it
was developed and is robust enough to be used as a starting point tool for the
development of customized templates for small, medium and large companies with
different types of projects, assets and competencies. In this way, the PRISM l
can provide the basic structure for multiple industry-wide use in project
selection as well as risk management.
Methodology:
The PRISM 1 Model
The
PRISM 1 Model was developed using the classic risk management process, which
includes identification, quantification, response and control. (Kerzner) The
identification of potential risks, both positive and negative, for any
construction project constitutes the most difficult part of this process. For
purposes of this paper, negative risk will be called ‘Risk’ and positive
risk will be called ‘Opportunity’. The PRISM l Model provides a
process to identify (Step One), quantify (Step Two), mitigate (Step Three), and
control (Step Four) risks and opportunities that can then be controlled
throughout the project.
Step
One: Risk Identification
Risk
is defined primarily as the potential for monetary loss or gain associated with
the project. Risk analysis uses a set of techniques and tools to identify,
prioritize and investigate opportunities, problems, and risks in order to assess
their cost and time impact on the project. To develop the risk management
framework, the potential sources of risk must first be identified and
categorized. Then a unique measurement system can be used to quantify the risks.
There
are three categories of risks associated with any project. Risks can be
classified as either knowns, known-unknowns, or unknown-unknowns.
(Kerzner)
·
· Known
risks are items or conditions that are understood but cannot be measured with
complete accuracy. Generally, such risks occur at a relatively high rate and
contain a wide range of possible outcomes. Labor productivity is a good example
of a known risk. The PRISM 1 model is especially good at working with this
category.
·
· Known-unknown
conditions or events are foreseeable because historical data documented their
occurrence on previous projects; however, they are not easily quantified.
Normally, such events have a relatively low frequency of occurrence but may
result in severe consequences. Earthquakes, hurricanes, unanticipated strikes or
an unusual challenge with a new sub-contractor are examples of this type of
risk. The PRISM ll model will be especially good at working with this category.
·
· Unknown-unknown
conditions or events generally cannot be predicted because historical data
do not suggest them as possibilities. These items can be catastrophic in nature
and may have a very low probability of occurring. Indeed, examples of
unknown-unknowns are hard to provide because historical data do not exist to
support their possibility. Remodeling, excavations and unique, never been built
before, one-of-a-kind projects would be examples of situations where a high
number of unknown-unknowns would exist. (Kerzner) The PRISM lll model will be
especially good at working with this category. Once an unknown-unknown happens
and is identified, it is logged into one project database and then becomes a
known or known-unknown for all future projects.
Currently,
in PRISM 1 development, risk identification is heavily dependent upon the
experience and perception of project managers and a quality historical database.
Unfortunately, this historical database is rarely fully developed and maintained
by most construction companies. In his research article "Practice,
Barriers, and Benefits of Risk Management Process in Building Service Cost
Estimation," Leung contends that approximately eighty percent of the
construction industry uses intuitive assessment in measuring risks. (Leung)
Qualitative
risk assessment models, which compare both risk and opportunity variables, are
presently used in other industries to assess relative project viability before
committing the resources required to develop a project plan and customer
proposal. (Ranasinghe; Baker) These models are usually completed by the project
manager working with the project team in order to assist the project team and
senior management make decisions regarding which opportunities should be managed
to ensure project success. However, these models should not be used as a set of
absolute rules or as a substitute for good business judgment but rather regarded
as guidelines for good qualitative decision-making. That is, these models have
been used to date primarily by senior management to make go-no go project
selection decisions, not to analyze and manage risks. They tend to be
qualitative in nature, not quantitative. The PRISM 1 Model adds to
the value of these tools by making the transition to valid quantitative output,
which provides a much more valuable decision-making to tool for the contractor.
There
are three steps involved in implementing most existing qualitative
Risk/Opportunity models.
1.
The first step is to identify and quantify the risks. A series of questions are
formulated, answered and quantified using a Likert scale (1-10) and a weighting
factor based on relative importance to the company. The risk scores are
calculated by multiplying this raw score times the Risk Probability (P) and the
pre-established Risk Impact (I). These scores are summed for a Total Risk Score.
As
with existing models, the users of the PRISM 1 Model develop and then
qualitatively answer a series of detailed questions, approximately 40, that will
identify the risks (20). Step two (below) repeats this identification process
for opportunities (20) as they relate to a potential project. Determining which
questions should be asked is one of the most difficult tasks in this process.
The questions are developed and reviewed by as many of the stakeholders who
impact the performance and profitability of a project to ensure
comprehensiveness as well as applicability to the company. Based on stakeholder
feedback, questions are stated in such a way so that they can be used for every
project and yet answered to reflect a specific project’s risk. Also, a wide
range of questions can provide the basis for analyzing groups of projects, past
and present, as a portfolio. The questions are then pared down by using the
Critical Risk Ranking Tool (Figure 2), which compares risks to each other (e.g.
Risk A to Risks B, C, D, E). This comparison can then be used to pare down the
final list of questions/risks (down to +/- 20 in total, with 10 risks and 10
opportunities)..
|
Figure 2. Comparative Risk Ranking |
2.
The second step is to evaluate opportunity in a similar fashion, using the
opportunity questions, weighting factor and Likert scale. The opportunity scores
are then calculated by multiplying the Possible Opportunity (P), times the
pre-established Impact (I). These scores are summed for a Total Opportunity
Score.
3.
The third step is to map the opportunity and risk scores. The total scores for
opportunity and risk are used as coordinates on the matrix provided within the
model, with the opportunity score placed on the y-axis and the risk score on the
x-axis. The location of this score on the matrix helps determine the potential
profitability of any one project opportunity compared to another and serves as
an indicator of the level of risk that will have to be managed in order to
ensure that project’s success. However, the PRISM 1 Model presents a further
innovation: it converts these data into dollars using cost indices. (See Figure
5 later in the paper) Inputting as much possible data from as many past projects
as possible improves the accuracy of this cost index; in this way, the data are
expressed in the language of business: money.
The
determination of the correct cost index constitutes the most difficult part of
the development of the model for a specific contractor. Fine-tuning of the model
must continue with each new project because the model actually helps to identify
risk and opportunity events that were not predicted to be significant originally
by the developers of the model. For example, the PRISM 1 model predicted the
correct potential profitability index for seventeen out of twenty sample
projects input to the model. The predicted profit margins fell within 1/2
percent of the actual on the profitability index scale. When analyzing the three
projects where the actual profit fell outside of the accepted variance range, it
was discovered that 2 of the projects contained an exceptional amount of
earthwork. The research partner-contractor was exceptionally good at and well
prepared for earthwork; therefore, he was able to create more profit from the
project than was predicted by the model. This was cause for revisiting the
opportunity questions. The result of this review was to include 2 new questions
that related to the relative amount of earthwork included in any project being
considered for bid. After these questions were incorporated, the prediction of
profitability fell to within 1/2 percent of the actual. The adjustment to the
model for the third project that fell outside allowable variance will be
discussed later.
After
several reviews and customizations to the lists of questions by various
stakeholders and clients, the following list of questions was compiled. This
list (Table l.) of questions is generally regarded by these companies to have
significant impact on project profitability:
Table 1. Potential Areas of Project Risk |
|||||||||||||||||||||||||
Project Feasibility |
|
||||||||||||||||||||||||
Building Type |
|
||||||||||||||||||||||||
Funding |
|
||||||||||||||||||||||||
Planning |
|
||||||||||||||||||||||||
Engineering/Architects |
|
||||||||||||||||||||||||
Type of Contract |
|
||||||||||||||||||||||||
Contracting Arrangement |
|
||||||||||||||||||||||||
Allowances |
|
||||||||||||||||||||||||
Regional and Local Business Conditions |
|
||||||||||||||||||||||||
Contractor Reliability |
|
||||||||||||||||||||||||
Owner Involvement |
|
||||||||||||||||||||||||
Regulatory Conditions |
|
||||||||||||||||||||||||
Forces of Nature |
|
||||||||||||||||||||||||
Site |
|
||||||||||||||||||||||||
Labor |
|
||||||||||||||||||||||||
Loss or Damages |
|
||||||||||||||||||||||||
Guarantees |
|
||||||||||||||||||||||||
Client |
|
Step
Two: Risk Assessment and Quantification
The
quantification process applied to the list of identified risks is challenging in
that each person assigning a value to the question will be subject to their own
prejudices and utility values. Therefore, the quantification process relies
heavily on Utility Theory. (Bernstein; Render; Dawood)
Utility
Theory allows decision makers to incorporate their risk preference and other
factors into the decision-making process. In order to measure the utility of an
outcome, these outcomes are assigned a value of utility: the worst given a value
of zero, the best a value of one. The utility assessment is completely
subjective in that the value set by the decision maker is not usually measured
on an objective scale. In fact, this assessment can be based on the personal
preferences of the decision maker, i.e. those (s)he is most comfortable
pursuing. For example, a construction company or decision-maker might place a
higher utility in performing projects within a certain geographical area or
designed by a certain designer. This might not be in direct relation to their
ability to perform the project.
Another
of the tools that a decision maker can employ is a decision tree. A decision
tree is a graphical representation of the analysis of choosing between two or
more alternatives. Each alternative is assigned a payoff amount and a
probability of receiving that payoff . To decide which alternative to select,
the expected monetary value (EMV) is computed by multiplying the payoff amount
(impact) by the probability. The sum of the decision ‘branches’ is then
compared to determine the best alternative. The following figure (Figure 3) is
an example of an analysis using a decision tree:
|
Figure
3. Decision
Tree |
Utility
theory assigns a preference for each desired result. It requires the decision
maker to determine the value of the probability of an event that makes him/her
differentiate between alternative 1 and 2. For example, in deciding the
preference between $0 and $10,000, one has to develop a utility curve that plots
monetary value versus utility value. After a utility curve has been determined,
the utility values from the curve are used in making decisions. Monetary values
are replaced with the appropriate utility values and then decision analysis is
performed as before. The utility curve indicates the amount of risk a person is
willing to take. The increasingly upward sloping curve indicates a risk seeker
while the curve that increases at a decreasing rate indicates a risk avoider.
The following graph (Figure 4) illustrates this point:
|
Figure
4. Risk
Preferences. |
Obviously,
using utility theory to determine which projects to pursue requires the
consideration of more than the possible profit. The decision to take a project
might have a higher expected monetary value than to not to take the project;
however, the willingness (utility value) of the contractor to accept the risk
might discount the overall return of the project. Thus, it would be wise for the
contractor to pass (no/go) on the project.
The
next step is to quantify the impact of these risks on the project (See Table 2)
As this table illustrates, the decision maker uses utility value to convert a
qualitative question of impact into a quantitative input to the overall
decision-making process. This part of the process is similar to the method many
industries, especially information technology and communications, have already
adopted using risk evaluation models. To date, however, the PRISM 1TM
Model is the first published attempt at producing a risk management/profit
predictor tool specifically for the construction industry.
Table 2. Qualification to Quantification Process |
Question One: CUSTOMER RELATIONSHIP (Sample) Based upon our current or prior relationship with this
customer, what is the probability that we will experience cost, schedule, or
performance problems? 0-10% 11-20% 21-30% 31-40% 41-50% 51-60% 61-70%
71-80%81-90% 91-100% If problems do occur as a result of our current or prior
relationship with thiscustomer, on a scale of 1 to 10, what could be the extent
of the impact on theproject's success? 0 1 2 3 4 5 6 7 8 9 10 |
Question Two: CUSTOMER READINESS Based upon the customer's readiness to undertake this
project, what is the probability that we could experience cost, schedule, or
performance problems? 0-10% 11-20% 21-30% 31-40% 41-50% 51-60% 61-70%
71-80%81-90% 91-100% If problems do occur as a result of the customer's
readiness to undertake this project, on a scale of 1 to 10, what could be the
extent of the impact on the project's success? 0 1 2 3 4 5 6 7 8 9 10 |
Most
existing models ask a series of questions that evaluate risk and a separate set
of questions to evaluate opportunity. The total scores from the questions are
mapped as coordinates on a matrix. (Aspinwall) When using the PRISM 1TM
Model, the project manager places the opportunity score on the right vertical
axis and the risk score on left vertical axis. (See Figure 5) The intersection
of the scores on the center profitability index determines the final profit
value of the risk/opportunity assessment for a specific project. The location of
this score on the index helps determine the quality of an opportunity and serves
as an indicator of the level of risk to be managed for overall project success.
|
Figure
5.
Profitability Predictor |
Thus,
this model utilizes a different approach to risk quantification using a
combination of Decision Tree Analysis, Utility Theory, Expected Monetary Value
and Risk/Opportunity Assessment Models.
On
a final note regarding risk identification, project estimates are often based
not only on the knowledge of the estimators and schedulers as well as on the
experience and data for similar projects completed previously, but also on a
large number of assumptions made regarding productivity rates and materials
prices. Some components of the projects are prone to variation, such as material
prices. Other items such as labor productivity rates can be sensitive to many
factors, including weather, temperature, state of the economy, union
involvement, and project duration and cost. This model is intended to provide a
logical mechanism for predicting the extent of these variations and forecasting
their impact on the project. The principal use of the output from the model is
not to discourage a company from bidding on projects with high risk but to
identify risk and encourage proactive risk management in a more cost effective
and timely manner.
Step
Three: Risk Response
A
spreadsheet program, such as Excel, can be used to rank the relative importance
of each risk area. Table 3 presents a sample output from the data collected
during the research.
Table
3 Weighted
Listing of Risks |
|
As
illustrated, a simple descending order ranking can set all of these risks up as
a prioritized list, making the list an ideal foundation for developing risk
mitigation strategies as part of the overall risk management plan. The
contractor can now develop an effective risk response to each identified risk
and opportunity on a cost/time effective prioritized basis. Many of these
identified as critical risks need to be addressed in the contract itself. If the
model is not used, the opportunity for mitigation using the actual contract
itself might be missed entirely. These responses can take the form of avoidance,
acceptance or mitigation. If mitigation is selected as the most effective
response, the contractor develops a response strategy that either reduces the
probability of the Risk event occurring (or increases the probability in the
event of an Opportunity) or reduces the impact if the event occurs (or increases
the impact in the case of an Opportunity).
Step
4: Risk Control
As
risks occur during the execution of the project, the strategies suggested in
Step 3 Risk Mitigation are implemented. The results are then evaluated and
documented for future projects. Experience has shown that the best way to
prepare future risk management plans is to access and apply the historical data
from past projects, the lessons-learned database. This is one of the important
benefits of using the PRISM 1TM Model: the database generated is
primarily graphic in format. This graphic facilitates rapid understanding and,
with additional information such ‘assumptions’ and ‘constraints’, can
become a useful lessons-learned database for future projects.
Summary:
The PRISM l Model
Information
from twenty (20) past construction projects has been used to date to provide
input to this phase of the model. The research conducted using the model
indicated that as more good historical data from past projects were generated
using the process and templates, the accuracy of the model as a predictor of
project profitability improved significantly. Indeed, contractors recognized the
value of the model as a powerful means of improving project procurement.
Several
issues needed to be addressed in the development of PRISM l. For example, the
model received input initially from project managers and estimators who were
intimately familiar with each of the projects being evaluated. As they answered
each of the risk and opportunity questions, they thought they were responding in
terms of the risks and opportunities that existed back at the time the company
was initially evaluating the projects as worthy of full estimating effort. It
became apparent that their judgment (utility theory) had been influenced by what
they actually knew to be valid risks and opportunities from the perspective of
hindsight. Therefore, the profitability predicted (See Figure 5) actually was
reflecting the potential profitability of the project after all of the risks and
opportunities had been realized. This probably should not come as to too much of
a surprise, since it would be difficult for the project managers or estimators
to divorce themselves from the realities encountered in the project. The data
point resulting from the input from past projects correlated very closely with
the actual profitability for each project.
As
the results from more projects were collected, the PRISM 1 model was fine-tuned
to reflect this additional information and suggestions for improvement in the
model. For example, when researchers found that several of the questions
regarding potential risks or opportunities have 0 or very low expected value,
the natural question arose: Is this issue really that important as it relates to
the way this company does business on this type of project? If not, eliminate
the question and look for others that suggest greater impact on the
profitability of the project. The other question that arose was: Are we missing
issues that should be included but were not because we assumed they were not of
major impact on the profitability of the project for this company? This
possibility was highlighted when several project results understated the actual
projected profitability of a project. Further study indicated that this
particular company was uniquely successful on projects that had a large amount
of earthwork, as mentioned earlier. Additional questions were formulated both on
the risk and the opportunity side. These modifications provided more accuracy in
predicting profitability on future projects with similar characteristics.
To
summarize the results to date, the PRISM 1 Model has proven thus far to be a
successful tool to assist management to:
·
· Make high
level go/no go decisions on bidding new projects (See Figure 5)
·
Identify
risks and opportunities
·
Quantify and
prioritize risks and opportunities
·
Allocate
risks to the party best able to handle the risk
·
Manage those
risks which cannot be transferred
·
Document
risk/opportunity events from past projects
·
Reduce the
cost of resolving disputes
·
Place a
limit on a firm’s financial exposure in the event of a claim, and
·
Archive
decision making wisdom of top management for use by future generations
As
modifications to the model are applied to future projects, time and experience
will further validate the accuracy of the predictions of the model. In any
event, the risk management process has been improved through the use of the
model as a tool to help create prioritized lists of risks and opportunities to
be mitigated. Rarely is there sufficient time and resources available to address
all risks and opportunities; therefore, the process should be extremely helpful
to management in prioritizing their risk management mitigation and control
efforts. At least project managers and estimators will have invested their
management time and resources on the right projects and in the risk areas that
have the greatest return on investment.
As
Pareto stipulated, 80% of the impact on an endeavor would be realized as a
result of only 20% of the possible influences. (Quality) Therefore, if we can
identify and mitigate the 20% most influential risk/opportunity events, we will
have gone a long way toward influencing the ultimate success of the project.
Additional
work and further refinement of the present PRISM 1TM Model will
continue in these areas. After all, this model was purposely designed to use the
best practices and information presently available combined with the traditional
time-tested tools of risk management. Why?...so that contemporary constructors
might avoid becoming future statistics on Dun & Bradstreet's report of
Construction Business Failures.
Ultimately,
when all is said and done, a model is only as ‘used’ as it is perceived to
be ‘useful’. Indeed, the authors recognize that many critical decisions are
governed by some very simple yet powerful variables that can overshadow more
significant ones. In interviews with over 200 contractors, the authors
determined that there are certain variables (over 600 identified to date) that
influence the contractor’s final decision as to how much profit shall be added
to the bid. Among these, there is an overwhelming influence is exerted by the
question: ‘How badly do we want or need this project?’ (Auchey) Indeed, this
influence exerted a significant impact on why the potential profit of one of the
projects was not accurately predicted by the PRISM l modeling and fell outside
allowable variance. The contractor wanted to win this project so badly that many
of the risks predicted were overshadowed by the need to win the bid. These
variables are now being quantified and incorporated into the model on a custom
contractor project basis in order to improve the accuracy of the PRISMTM
Model and the effectiveness of the process of procuring successful projects.
References
Aspinwall,
Elaine M., Joanna C. Bennett, George A. Bohoris, and Richard C. Hall.
, Risk Analysis Techniques and Their Application to Software Development. European
Journal of Operational Research, 1996, February, 467-475.
Auchey,
F. L. Survey:
Variables Influencing Bid Strategies. Independent surveys conducted with
over 600 Associated General Contractor (AGC) members in Florida, North Carolina,
South Carolina in Virginia from 1986 through 1989.
Bajaj,
D., D. Lenard, and J. Oluwoye.
An Analysis of Contractors' Approaches to Risk Identification in New South
Wales, Australia. Construction Management and Economics, 1997, October,
363-369.
Baker,
Scott, David Ponniah, and Simon Smith.
Risk Response Techniques Employed Currently for Major Projects. Construction
Management and Economics. 1999, November, 205-213.
Bernstein,
Peter L. Against
The Odds: The Remarkable Story of Risk. 1998, New York, John Wiley &
Sons, Inc.
Dawood,
Nashwan. Estimating
Project and Activity Duration: A Risk Management Approach Using Network Analysis.
1997, Division of Civil Engineering and Building, School of Science and
Technology, The University of Teesside.
De
la Garza, Jesus M. and Khalil G. Rouhana.
Neural Networks Versus Parameter-Based Applications in Cost Estimating. Cost
Engineering,1995, February, 14-18.
Dexter,
William F. Risk
Management: A Mine Field. Consulting-Specifying Engineer, 1999, May.
Diekman,
James, Roger S. Pecosk, and Anthony D. Songer.
Risk Analysis for Revenue Dependent Infrastructure Projects. Journal of
Faculty of Civil, Environmental, and Architectural Engineering, University
of Colorado. 1997, January, 377-382.
Duffield,
Colin F., Aminah Fayek, and David M. Young.
A Survey of Tendering Practices in the Australian Construction Industry. Engineering
Management Journal, 1999, December,29-34.
Engineering
News Record,
April 7, 1997, Vol. 238, #14, 9.
Kerzner,
Harold. Project
Management. 1998, New York: John Wiley & Sons, Inc.
Kim,
Soon. Risk
Management in Construction: An Approach for Contractors in South Korea. Cost
Engineering,2000, January, 38-44.
Leung,
H.M., C.K. Mok, and V.M. Rao Tummala.
Practices, Barriers, and Benefits of Risk Management Process in Building
Services Cost Estimation. Journal of Department of Manufacturing Engineering,
1996, City University of Hong Kong, April, 161-175.
Quality
for Project Managers.
1998, ESI International. 2.25.
Ranasinghe,
Malik. Risk
Management in the Insurance Industry: Insights for the Engineering Construction
Industry. Journal of School of Building and Real Estate, 1997, National
University of Singapore. February.
Render,
Barry and Stair, Ralph M. Jr. Quantitative
Analysis for Management.
2000, Seventh Edition, Prentice Hall.
Addresses
of authors:
Dr.
Flynn L. Auchey, 122
Burruss Hall, Department of Building Construction, Virginia Polytechnic
Institute & State University, Blacksburg, VA, 24061-0156, USA
Dr.
Gloria J. Auchey, PMP, President,
The Success Institute of America, Inc., 1500 Midpines Road, Blacksburg, VA,
24060, USA