|
Prequalification
of Bidders for Public Works Projects
Scott Kramer and Natasha White-McCurry Auburn
University Auburn,
Alabama |
According
to the Alabama Building Commission, the need for prequalification of bidders
on public works projects at the state level has become apparent due to the
number of projects which have been marred by substandard quality, devastatingly
late completion, or cost overruns. Many public owners feel that, as a result of the Competitive
Bid Law, they are forced to accept the lowest bidder regardless of
contractor qualifications. Much of
the private sector and some large state departments in Alabama, such as the
Department of Transportation, already utilize the practice of prequalification;
but other public entities, such as school boards and correctional facilities,
typically do not. This paper
describes the methodology and creation of prequalification guidelines for the
Alabama Building Commission that can be used on public works projects throughout
the state. Key
Words:
Bidding, Prequalification, Public Construction |
Introduction
Background
and Research Problem
For years, the public owner has
been faced with many challenges in an attempt to ensure that projects are
completed successfully – on time, within budget, and meeting quality standards
set forth in the contract documents. One
method of improving construction performance is to prequalify general contractor
and subcontractor bidders. Prequalifying
bidders is the process by which the owner, or a team of individuals selected by
the owner, screens the candidate constructors according to a given set of
criteria prior to any competitive
bidding or price negotiations. The
objective is to determine a contractor’s competence to perform the work in a
satisfactory manner should they be awarded the contract.
The Public Works Law (Title 39,
1997) as amended on April 22, 1997, now acknowledges prequalification as an
acceptable practice for public works projects in Alabama.
Although the Alabama Building Commission neither endorses nor discourages
the practice of prequalification, they requested that a research team create a
set of guidelines taking into account the best practices of prequalification
from other southeastern states. These
guidelines would then serve as a basis for building committees that solicit
construction bids infrequently, such as local school boards. To
achieve this goal, individuals from academia, private industry, and government
service were chosen to conduct the necessary research.
Those serving on the research team included:
|
Literature
Review
Since
1964, the standard prequalification document for use in commercial building
construction has been the AIA Document A305 (AIA, 1986).
Nevertheless, while the traditional AIA A305 served as the basis
for the new Alabama prequalification guidelines, information was also extracted
from studies conducted by Jeffery S. Russell.
Russell has conducted numerous studies on prequalification of bidders and
has published several journal articles on the subject (Russell, 1990; Russell
& Skibniewski, 1990; Russell, Skibniewski, & Cozier, 1990; Russell &
Jaselskis, 1992; Russell & Skibniewski, 1998).
Russell (1996) has compiled the highlights of these and other journal
articles into a book titled Constructor Prequalification – Choosing the Best Constructor and
Avoiding Constructor Failure.
It is an invaluable reference for anyone interested in prequalifying
contractors. However, the research
team was charged by the Alabama Building Commission to go beyond traditional
literature searches and gather information, procedures, and guidelines from
specific individual state building commissions and government agencies.
Research
Methodology
Instrument
– Request for Information
In
order to collect information from public works sources, a request for
information was sent to various state building commissions.
The responses were collected and filed into 3-ring binders for analysis
and reference. The requests were
primarily sent to southeastern states – Alabama, Tennessee, Georgia, Florida,
Mississippi, Louisiana, Arkansas, Texas, Kentucky, North Carolina, and South
Carolina. However, as information
was received, the research team was led to other sources of information in
Maryland, Kansas, Virginia, and Missouri. This
information was then organized and labeled as Source Documents.
The authors then analyzed the source documents and prepared a rough draft
of prequalification guidelines from the synthesis of information.
The authors met with the entire research team on a biweekly basis to
review the rough drafts of the guidelines and to make necessary changes.
The
authors also received other relevant literature in response to a separate
request for information that was sent to various state departments that handle
construction projects. Table 1
shows the various departments from which information was received as a result of
this request. In addition, the
authors reviewed section 39-2-4 of the Code of Alabama, and other
prequalification formats from the private sector. Two of the most significant private sector responses came
from the United States Postal Service (USPS) and the Federal Express Corporation
(USPS, 1988; FedEx, 1998).
Table
1 |
||||
|
DOT |
Education |
Prisons |
General |
Alabama |
X |
X |
|
|
Arkansas |
X |
X |
X |
X |
Florida |
X |
|
X |
X |
Georgia |
X |
X |
|
X |
Kansas |
|
|
|
|
Kentucky |
X |
X |
X |
X |
Louisiana |
|
|
|
|
Maryland |
|
|
|
|
Mississippi |
|
|
|
X |
Missouri |
|
|
|
X |
North Carolina |
|
|
|
|
South Carolina |
|
|
|
X |
Tennessee |
X |
X |
X |
X |
Texas |
X |
|
X |
X |
Virginia |
X |
X |
X |
X |
X = Information received from state department |
Once
the prequalification guidelines were in a rough draft format, the authors made
several trips to visit construction firms in order to review the guidelines and
solicit suggestions from practicing construction professionals.
This was imperative because the guidelines were to be implemented in
Alabama where many of the firms bid work. The
contractors who provided feedback were: Brasfield & Gorrie, Connor Brothers
Construction Company, Parker Building Company, Bailey-Harris Construction
Company, Doster Construction Company, and Hoar Construction Company.
The representatives of each of these contractors indicated that the
proposed prequalification questionnaire was very thorough, yet simple and
concise. The contractors stated
that they are familiar with submitting much more elaborate questionnaires and
would have no trouble submitting this form in a timely manner.
Also, the reaction of each contractor was favorable toward the overall
idea of prequalification. In fact,
they all expressed the desire to have public prequalification implemented as
soon as possible. They felt that,
by eliminating the unqualified competitors, competition would be better and
quality would improve for the taxpayers.
Analysis
and Implementation of Prequalification Guidelines
The
following paragraphs outline the items that were identified by the research team
as crucial to the successful creation of prequalification guidelines for
Alabama. However, these items could
be used by any state or public entity that is interested in prequalifying
construction bidders.
Evaluation
Team
The Alabama Building Commission
suggested that the owner’s evaluation team should be comprised of two
owner’s representatives and the design professional of record.
The owner’s representatives may be a construction manager, city
engineer, county engineer, superintendent of education, facilities manager,
teacher, or outside awarding authority.
Evaluation
Criteria
The
research team decided, based on the fact that the owner’s evaluation committee
would typically be somewhat unfamiliar with procuring construction services,
that the best approach to prequalification would be the one with the least
amount of subjectivity. Many
different forms were analyzed in an effort to compile a set of questions that
would be best suited to meet the prequalification needs of public works projects
in Alabama. Some owners showed a
very specific interest in equipment (AL DoT, 1998) and others had an interest in
safety (Union Camp, 1997). There
was some interest in specific insurance types and
coverage (FedEx, 1998) and others had a specific interest in minority business
enterprise participation and commitment (USPS, 1998). The researchers decided that because these matters have
specific requirements set forth in the contract documents, there was no need to
request extensive information concerning such topics.
The decision of the research team was to ask only basic questions, such
as: “Does your organization have a written safety program?”, “Is a copy
available upon request?”, and “What was your EMR for the last three
years?”
After
analyzing the source documents, the research team felt that the evaluation
process would be much easier to conduct if there were a standardized form to
fill out (Appendix A). Since the
format of each contractor’s data is identical, the evaluation team will be
able to spend less time looking for information and more time evaluating it.
Also, the authors arranged the questions in the guidelines in such a way
as to receive a more structured response, thereby making the analysis easier for
the evaluation team. The key
elements that were developed for the Alabama guidelines were:
General Information, Experience Record, Financial Status, Employee
Qualifications, Safety Performance, and References.
Collecting
Contractor Data
Section
39-2-4 of the Code of Alabama states that, for projects in excess of
$50,000, the advertisement for prequalification must be published once a week
for three weeks in a newspaper of general circulation in the county or counties
in which the project, or any part of the project, is to be performed.
For projects in excess of $500,000, the notice must also be published at
least once in three newspapers of general circulation throughout the state
(Title 39, 1997). The advertisement
for prequalification must inform the contractors where the prequalification
information can be reviewed and obtained. Also,
it is recommended that the last advertisement for prequalification be published
five weeks prior to the bid date. This
allows one week for the contractors to complete and return the forms, two weeks
for the evaluation committee to review the forms and contact references, and two
weeks for the qualified applicants to bid the job.
This process is illustrated in Figure 1.
|
||
Figure
1. Timeline for the
Prequalification Process |
Analyzing
Contractor Data
Due
to the inherent nature of the projects that will necessitate the use of these
guidelines, the Alabama Building Commission recommended that the owner
prequalify bidders on a project-by-project basis.
However, the research team recommended that annual
prequalification of public works projects may be appropriate for an owner that
expects to bid several similar projects within a given year.
The
data that the evaluation committee collects will be analyzed from both a
qualitative and a quantitative perspective.
Much of the information provided by the contractor is subjective and
therefore will be analyzed qualitatively. The
rest of the information, however, will be analyzed quantitatively using models
similar to those used by the United States Postal Service (USPS, 1988).
The owner will also evaluate the contractor's financial statements in
order to make projections about the future.
Qualitative
It is important to thoroughly
review the items provided in the contractor’s qualification packet that relate
to current projects and previous projects that were similar in scope.
Also, replacing key personnel is a sign of danger.
This is a key factor that an owner should be aware of when evaluating the
quality of a contractor. Because the plans are often not complete at the time of
prequalification, the research team chose not to require the contractors to
submit a specific construction team
that would staff the project should their company be awarded the contract.
Depending on how much time elapsed between the prequalification process
and the notice to proceed, many changes could take place within a company.
However, the recommendation was that each contractor would submit a list
of key personnel who may staff the
project as well as the resumes of those key personnel.
Since any individual on this list may be appointed to this project, the
owner’s evaluation committee should make certain that each one of the
individuals on this list has the necessary skills to carry out the work
properly.
Quantitative
Some
aspects of the prequalification data will be evaluated as pass or fail.
For example, any firm who does not have a general contractor license to
do business in the State of Alabama, will be refused the right to bid.
Also, if an applicant has a negative net worth, the application will be
rejected. Should either of these
situations arise, there is no need to analyze the data any further.
The applicant will automatically be disqualified.
The
recommended method to be used in the quantitative analysis for public works
projects in Alabama is similar to that presented by the United States Postal
Service (USPS, 1988). However, the
scale has been changed to a five point scale: 5 = excellent, 4 = good, 3 =
average, 2 = fair, 1 = poor, 0 = unacceptable.
Prior to analyzing the contractors’ data, the first step that the
owner’s evaluation committee should decide upon is the minimum score that will
be acceptable for a bidder. The
recommended procedure for determining this value is to enter the lowest rating
that is acceptable for each given component into the evaluation matrix and
multiply the rate of each given component by its corresponding relative weight.
The sum of these products will be the lowest minimum acceptable score.
An example of this is shown in Appendix B.
The Minimum Acceptable Score that would be acceptable for bidders
prequalifying on this hypothetical project would be the sum of the scores of the
individual components, or 925. Note
that the total points possible in the Weight column does not have to be
100. Therefore, the relative worth
of each individual component can be adjusted rather easily without being
concerned about decimal values or percentages.
The
evaluation matrix can be modified to address the unique needs of the owner just
as the questionnaire can. The
example matrix found in Appendix B lists all of the key elements corresponding
to the questionnaire (Appendix A) and weights them according to their relative
importance. While analyzing the contractor-supplied data, the evaluation
committee is able to rate the contractor on each key element according to the
5-point scale mentioned previously. The
rating for each item is entered into the first column under the heading that
correlates to each contractor. The
rate is then multiplied by the relative weight for that item and entered into
the last column relating to that particular contractor. Then, the sum of the products of the rates and the weights
will yield the total rating, just as before.
Since Bidder A falls below the acceptable value, the score would not
prequalify the bidder for this project. On
the other hand, the score for Bidder B is sufficiently above the minimum
acceptable value; so Bidder B would be deemed qualified to bid.
Although Bidder C only misses the mark by one point, the score is
not sufficient to be qualified on this project.
However, bidder D would qualify with a score of 925, which is equal to the minimum
acceptable score.
Notifying
the Applicants
After
the Owner’s evaluation committee has analyzed each questionnaire, made all
necessary contacts, and has determined the appropriate ratings, the committee
should notify the contractors, in writing, as to whether they have been
prequalified or not. Since Section
39-2-4 of the Code of Alabama states that once a bidder has been
prequalified, they are deemed “responsible” for purposes of bidding (Title
39, 1997). Those that are
prequalified will be able to obtain bidding documents and begin to prepare
estimates immediately.
Legal
Recourse
Since
the Alabama Public Works Law states that it is mandatory to publish the
evaluation criteria, one could easily falsify the information to meet the
criteria. Contractors, that the
authors interviewed, suggested that legal recourse be added to the questionnaire
in order to ensure that the information is legitimate. The research team decided that a signatory statement similar
to the one in the AIA A305 would be added, along with a requirement for
notarization. Nevertheless, the
evaluation committee should carefully verify all information provided by
conducting reference checks.
Disclaimer
The
contractors, who were interviewed by the authors, felt that it was important to
state that no representation is made about the results of prequalification.
It should be noted that, although prequalification certainly helps
eliminate many problems, it is not infallible.
It is, in fact, possible that even though an owner may go to great
lengths to prevent failure – unfortunate situations do occur.
These guidelines do not guarantee
the success of any project. Nevertheless,
it does eliminate the contractors with the greatest likelihood of failure.
Conclusions
and Recommendations
Previous
research shows that, on average, prequalification accounts for about 1% of the
total cost of a project, and the payback has often been astounding (Russell,
1996). In fact, since the USPS
implemented their prequalification program in 1988, they report studies
revealing an average increase of 4.5 % versus their previous method of postqualifying
contractors, which resulted in project cost increases of 10% to 15% (Russell,
1996). Overall, the USPS reports
having reduced cost escalation and improved schedule, which are two of the
primary reasons for implementing the system.
Future
possibilities for research regarding prequalification of bidders may include
computerized applications. Public
owners could improve the process outlined in this paper by making the guidelines
accessible on the Internet. Furthermore,
the format provided in Appendix A can be used not only to prequalify general
contractors, but subcontractors as well. Specific-need
questionnaires (to be used for owners that are particularly interested in
safety, schedule, etc.) may also evolve from further research.
The
implementation of prequalification guidelines will enable those who are
entrusted with public funds to make responsible decisions regarding which
contractors are qualified and which contractors are not.
From interviews conducted with various contractors throughout Alabama,
the authors found that the practice of prequalification was readily accepted
and, in fact, anticipated for public works projects.
Therefore, having a prequalification process and consistent guidelines
will hopefully cause public owners in Alabama to put forth the time and effort
to prequalify bidders and help alleviate substandard quality, late completion
times, and cost overruns.
References
AIA.
(1986). AIA
Document A305 – Contractor’s Qualification Statement, 1986 Edition.
The American Institute of Architects.
FedEx.
(1998). Request for Qualifications.
Construction Services Federal Express
World Headquarters.
Russell,
J. S. (1996). Constructor Prequalification – Choosing the Best Constructor and
Avoiding Constructor Failure. American
Society of Civil Engineers Press.
Russell,
J. S. (1990). Model for Owner Prequalification of Constructors. Journal
of Management in Engineering, ASCE, 6(1), 59-75.
Russell,
J. S., and Skibniewski, M. J. (1988). Decision Criteria in Contractor
Prequalification. Journal of Management in Engineering, ASCE, 4(2), 148-164.
Russell,
J. S., and Skibniewski, M. J. (1990). QUALIFIER-1: Constructor Prequalification
Model. Journal of Computing in Civil
Engineering, ASCE, 4(1), 77-90.
Russell,
J. S., Skibniewski, M. J., and Cozier, D. R. (1990). QUALIFIER 2:
Knowledge-Based System for Constructor Prequalification. Journal
of Construction Engineering and Management, ASCE, 116(1), 157-171.
Russell,
J. S., and Jaselskis, E. J. (1992). Predicting Construction Contractor Failure
Prior to Contract Award. Journal of
Construction Engineering and Management, ASCE, 118(4), 791-811.
Title
39 (1997). Code
of Alabama, 1997 Amendment. Section
39-2-4, Filing of guaranties by bidders; prequalification procedures and
criteria; responsibility of prequalified bidders; revocation of prequalification;
rejection of bidder. p. 96-98.
Union
Camp (1997). Contractor’s Review and Evaluation Form. Union Camp
Corporation, Corporate Engineering Division.
USPS
(1988). Pre-qualification
Criteria, United States Postal Service. Procedure 210.25 –
Advertising for Prequalification Statements, Procedure 210.35 – Advisement of
Prequalification, Procedure 210.30 Evaluation of Prequalification Statements,
Procedure 210.20 – Prequalification Planning. HB RE-14, TL-1, August 1988.
Appendix
A - Contractor's Statement of Qualifications
1. General Information: |
Submitted to: ______________________________________________________ Project Name: _____________________________________________________ Project Number: ____________________________________________________ 1.1
Name of Firm: Street
Address: _____________________________________________________ Mailing
Address (if different from above): _______________________________ Area
Code & Telephone Number: ______________________________________ Facsimile
Number: __________________________________________________ Person(s)
to Contact: ________________________________________________ 1.2
a. Date your firm was
organized or started:_______________ b. Legal Form of Business: Corporation:_______ Individual:_________ Partnership:________ Joint Venture: ______ Other:____________ c. If a corporation: State of Incorporation: __________ Date of Incorporation: __________ Federal I.D. #: __________
1.3 a. Subsidiary of another company? Yes _____ No _____ b. Parent Company Name:____________________________________________ c. Sister Company in related business? Yes _____ No_____ d.
Sister Company Name: ____________________________________________ 1.4 a. In what states are you licensed to do business?__________________________ b. Alabama Contractors' License Number:_____________________________ 1.5 Names of officers, owners, partners, and principals. Identify relationship of each to firm and if active in firm:____________________________________________ 1.6 Other than persons listed above, number of full-time office employees:__________ 1.7 Number of full-time, permanent field employees:___________________________ 1.8 If yes to any of the following questions, please attach a brief explanation and include the names, addresses, and phone numbers of persons who might be contacted for additional information. a. Are there any claims, judgments, arbitration proceedings or suits pending against your organization? Yes _____ No _____ b. Within the last five years, has your organization filed any law suits or requested arbitration related to construction contracts? Yes _____ No _____ c. Within the last five years, has your organization ever
failed to complete any work awarded to it?
Yes _____ No _____ d. Has your organization ever been adjudged a bankrupt
or filed a petition in bankruptcy?
Yes _____ No _____ e.
Within the last five years, has your organization been
assessed liquidated damages for failure to complete
a project by the contracted date?
Yes _____ No _____ f.
Has your organization, in the last three years, received a
final order for willful and/or repeated violation(s) issued by
the United States Occupational Safety and Health Administration
(OSHA) or by the Alabama Department of
Labor or any other government agency?
Yes _____ No _____ g.
Have any Performance or
Payment Bond claims ever been
paid by any surety on behalf of your organization?
Yes _____ No _____ |
2. Contractor’s Experience |
2.1
a. Number of years of doing
work similar to that work for which you are prequalifying:________ b.
Number of projects that your organization has completed that are similar
to the work for which you
are prequalifying:__________ 2.2
Complete the attached form, form
100, Major and/or Similar Projects Completed Within the Last Five
Years. (Computer-generated data
in this format is acceptable.) 2.3
Complete the attached form, form
200, Major Projects in Progress. (Computer-generated data in this
format is acceptable.) 2.4
On a separate page, briefly describe your approach to project scheduling,
monitoring, and control to ensure timely completion.
Include how your firm will keep the owner abreast of any concerns related
to the schedule (1 page or less). 2.5
a. What % of the contract
amount do you typically perform with your own forces? __________ b.
Identify work normally performed with your own forces on projects similar
to
the
one for which your firm is prequalifying. __________________________ 2.6
a. Does your firm have a
written quality control program? Yes
_____ No _____ b.
Is a copy available upon request?
Yes _____ No _____ 2.7
Does your organization have a minority recruiting program?
Yes _____ No _____ |
3. Contractor's Financial Status |
3.1
Enclose your latest audited financial statement.
Note and explain any key factors that have changed. 3.2
a. Who is your bonding
company? ______________________________________ b.
Who is your bonding agent? _________________________________________ c.
Has your bonding company changed in the past three (3) years? ______
If YES, why?
_____________________________________________________________ __________________________________________________________________ d.
Indicate your surety’s A.M. Best rating: _______________________________ e.
Does your surety have a license to do business in the State of Alabama?
______ 3.3
a. What is the total bonding
capacity of your firm? _________________________ b.
What is your current bond amount in use? ______________________________ c.
What is the individual job bonding capacity of your firm?
__________________ d.
What is the maximum you have bonded on any single project? ______________ e.
What is your average annual volume for the past five years?
________________ f.
What is your organization’s current backlog (total value of work in
progress and
work under contract)? _____________________________________________ 3.4
What is your policy on bonding subcontractors? ___________________________________________ __________________________________________________________________________________ |
4. Employee Qualifications |
4.1
On a separate page, provide an organizational chart of project personnel
for a project similar to the one for which you are prequalifying (1 page or
less). 4.2
Include resumes of your key personnel who may staff this project.
Provide at least three (3) project-related references for each proposed
team member. |
5. Safety |
5.1
a.
Indicate your Experience Modification Rate (EMR) for the past three
years. 20___
- __________ 20___
- __________ 20___
- __________ b.
EMR Anniversary Date: __________ 5.2
a. Does your firm have a
written safety program? Yes
_____ No _____ b.
Is a copy available upon request?
Yes _____ No _____ |
6. References |
6.1
Does the owner have concurrence of the Contractor to contact any and all
references included? (Yes / No) 6.2
BANK: Firm
name _____________________________________________________ Street
address ___________________________________________________
City/State/Zip
___________________________________________________ Phone
__________________________________________________________ Contact
_________________________________________________________ 6.3
SUBCONTRACTORS (3 each) Firm
name _____________________________________________________ Street
address ___________________________________________________
City/State/Zip
___________________________________________________ Phone
__________________________________________________________ Contact
_________________________________________________________ 6.4
VENDORS/SUPPLIERS (3 each) Firm
name _____________________________________________________ Street
address ___________________________________________________
City/State/Zip
___________________________________________________ Phone
__________________________________________________________ Contact
_________________________________________________________ 6.5
OWNER/CLIENT (3 each) Firm
name _____________________________________________________ Street
address ___________________________________________________
City/State/Zip
___________________________________________________ Phone
__________________________________________________________ Contact
_________________________________________________________ 6.6
LEGAL COUNSEL Firm
name _____________________________________________________ Street
address ___________________________________________________
City/State/Zip
___________________________________________________ Phone
__________________________________________________________ |
The
undersigned certifies under oath that the information provided herein is true
and sufficiently complete so as not to be misleading. Signature
________________________________________________ Witness
__________________________________________________ Notary
___________________________________________________ |
Appendix
B – Sample Evaluation Matrix |
|||
|