ASC Proceedings of the 23rd Annual Conference
Purdue University - West Lafayette, Indiana
April  1987              pp 104-113

 

A SERIES OF LOTUS 1-2-3 TEMPLATES FOR TEACHING GOOD ESTIMATING PROCEDURES

 

Bill McManus
 The University of Oklahoma
Norman, Oklahoma

 

A construction pricing and bidding system based on the popular spread-sheet Lotus 1-2-3 is presented. It uses the full range of 1-2-3's capabilities to aid the estimator in the organization and prepara­tion of detailed estimating and bidding documents. This is done in five distinct steps: subdivision of the work, calculation of direct costs, estima­tion of indirect costs, assessment of subcontract offers, and the mark up of the bid.

Unlike most computerized estimating systems, CONEST (the name of this system) is not based on a data base of unit prices. Material costs must be supplied from an external source. Labor costs are based on crews and productivity factors defined by the estimator.

Designed to both teach and implement good estimat­ing procedures, CONEST requires attention to be given to all significant cost components. It further aids the instructor in that student estimates are all in the same format and can be graded by exception with the aid of the program.

 KEY WORDS - Cost estimating, Computer, Lotus 1-2-3, Work package, Work breakdown structure

 

 

INTRODUCTION

 

Most computerized estimating systems are not conducive to the teaching of good estimating practices. They are based on databases of unit prices and the critical -part of using these systems is the development and maintenance of these lists of data. This process is too time consuming to be undertaken as part of a one semester estimating course. The alternative is to use a database developed by someone else. In this case the student estimator is merely supplying his takeoff data to the system which then magically figures out how much the project is going to cost.

 

Although designed to be used in the construction industry, CONEST is suited to the classroom environment. It is an estimating system that lets the students do much of the thinking while giving them the tools and the structure with which they can produce a superior, auditable, and easily evaluated estimate.

 

This paper is addressed to teachers of construction estimating. An understanding of estimating procedures and the use of electronic spreadsheets is assumed.

 

Description of the System

 

CONEST is an integrated series of menu and macro controlled Lotus 1-2-3 templates designed to aid both general and specialty construction contrac­tors in the estimating, pricing and bidding of work.

 

The CONEST system is based on Lotus's spread sheet partly because of 1-2-3's power and partly because of its popularity--there are millions of copies in use. CONEST is not copy protected and since it is built of standard Lotus 1-2-3 functions and macros, the sophisticated 1-2-3 user should have no problem customizing the system to suit his unique needs.

 

Requirements

 

The minimum computer system required to run CONEST consists of a MS-DOS computer with 256k of Random Access Memory (RAM), two floppy disk drives, a printer capable of printing 132 columns in compressed print mode, and Lotus 1-2-3 version 1-A (or a completely compatible "work alike").

 

While CONEST has been designed to work well in this minimum configuration, its performance and capacity can be substantially enhanced with more RAM, a faster processor, and/or hard disk storage. CONEST swaps portions of the spread sheets in and out of memory to get the maximum amount of function out of the minimum amount of RAM. Even using these techniques only 100 work packages (more than enough for most student estimates) can be analyzed at one time with the 256k RAM version. This limitation can be overcome by subdividing the analysis and consolidating the data on the summary sheet. This is not a complicated process since it can all be done through menu selections.

 

Evolution

 

CONEST was developed by the author while earning a Masters degree in Construction Management at Texas A&M University. The first version was a system based on the work package concept (discussed in more detail in the section on work breakdown structure) and implemented in Multiplan. This system was developed under the Microsoft Disk Operating System (MS-DOS) and transferred to Digital Research's Control Program for Micro Computers (CPM).

 

The system consisted of separate spread sheets for each work package which were then consolidated in a summary spread sheet. These summary data were then combined with an indirect cost report on a top sheet that provided for adjustments and markup.

 

This early version of CONEST was used by nearly one hundred students to prepare realistic esti­mates and bids for several small commercial projects. This provided the author with the opportunity for considerable testing and analysis of the strengths and weaknesses of the system.

 

Three major weaknesses were identified in this early version of the system. First, a moderate level of skill in the use of Multiplan was needed to build an estimate. Second, the process was relatively slow due to its implementation in CPM and to the way summary information was developed using Multiplan's file linking capability. Third, subcontracts were included in the work packages making it too time consuming to effectively deal with additional sub contracts in the last minutes before a bid was due.

 

After careful consideration of the processes involved, a decision was made to rewrite the system in Lotus 1-2-3. This was done primarily so that the macro capability of Lotus could be used to simplify and speed up the process.

 

This new version required a complete restructuring of the system. Instead of using the file linking feature of Multiplan, summary data are exported from each work package as it is defined. This creates a data base that grows with each addition­al work package and gives the estimator a running total of his direct costs as he goes.

 

 

THE CONEST MODULES

 

The CONEST system consists of four main modules which are accessed through an umbrella module named CONEST. The four main modules are listed in Table 1.

 

Work Breakdown Structure (WBS)

 

The first step in preparing a construction estimate is the subdivision of the work into manageable activities. In the CONEST program, each of these activities is called a Work Breakdown Item (WBI). The list of WBIs that define the job is called the Work Breakdown Structure (WBS).

 

 

Organization

 

The estimator should designed these WBI's so that the same item can be used for material quantification and pricing, estimating level of effort, scheduling, and cost control.

 

"Each [Work Breakdown Item] is composed of like activities with similar productivity factors, has a defined beginning and end, is under the supervision of one first level manager (foreman), and can be objectively measured for progress reporting" [1].

 

The structure required to most efficiently quantify the material requirements is not necessarily the same as the structure needed to most efficiently schedule the work or measure the level of effort. Compromises must be made so that the same WBIs can be used throughout the life of the project. This not only keeps the estimator, scheduler and cost accountants from duplicating the others work, but also allows for meaningful feedback to be used on this and future jobs.

 

CONEST is designed Co encourage this sort of organization. Each work package is limited to one labor productivity factor, and provisions are made to include scheduling information in the form of a list of prior work items.

 

The WBS module produces a list of the work packages that make up the job. Each work breakdown item consists of a sequential WBI number, two 3 digit cost codes, a description, and the unit of measure to be used to estimate the labor requirements. The following (Table 2) is a brief example:

 

 

Operation

 

The system opens two windows. Previously prepared WBSs are imported into the first window. Items that are needed for the current job are then copied' into the second window. The system comes with a 199 item WBS based on the Construction Specification Insti­tute's Uniform Cost Index (UCI). These items are "Broadscope section titles" and as such are too general in nature to be used as actual work breakdown items. They have been included for two reasons. The first is to serve as an example to demonstrate the macro controlled production of an "Out-WBS" from an "In-WBS". The second is to serve as a basis for the assignment of cost codes so that all estimates produced with the system can be compared and evaluated in the ANALYSIS module.

 

After a number of WBSs have been developed and saved, a new WBS can be organized by combining portions of established WBS files. The system sorts and numbers the lists automatically. The WBS module can be used to prepare an activity list for scheduling the job as well as a work breakdown structure for pricing the general contractor's own work.

 

Cost codes

 

The cost codes can be anything that will help to summarize and track the WBIs and be reconcilable with existing codes used for accounting or cost control. This reconcilability is of utmost importance and can be provided for with good cost codes and a good work breakdown structure [2].

 

For simplicity in the examples, the first cost code (CC1) is the major (UCI) Division and the second cost code (CC2) is the major classification within that Division. The program is set up to use two 3 digit numbers but can be easily modified to accept longer numbers. Regardless of the cost code scheme used, it should be well thought out and used for all estimates produced. In a busi­ness setting this will allow the analysis and comparison of like items from multiple jobs. In an educational setting this uniformity of cost codes will allow student produced estimates to be evaluated by exception. This will increase the accuracy and detail of the evaluation as well as substantially decreasing the time it takes to identify and trace errors to their source.

 

Description and unit of measure

 

The description should be brief but adequate to clearly define the item of work. The program will accept a description up to 255 characters long but most of the reports will print only the first 24 characters.

 

The unit of measure is that unit with which the level of effort will be forecast. Since the most critical part of any construction estimate is the prediction of the manpower to be used, the WBIs in the CONEST system are based on this measure. For example, the unit of measure for the painting of stripes in a parking lot would be linear feet of stripe as opposed to gallons of paint.

After the work breakdown structure for the job to be estimated is created, it is exported for use in the next module--WORKPACK.

 

Work Package Generation (WORKPACK)

 

Step two in the production of an estimate using CONEST (after defining the Work Breakdown Structure) is the detailed definition of each WBI. With this module, the estimator creates work_ packages out of the WBIs by adding specific quantitative data to the general description given to each WBI in the WBS module. This module produces one page reports describing each of the

work packages. The reports are subdivided into eight blocks: Description, Labor, Materials, Equipment, Subcontracts, Prior Work Items, Notes, and Total Cost This Work Package (Figure 1).

 

Create labor table

 

The first thing that must be done to prepare to use WORKPACK is the modification of the Labor Table to reflect the crews and wage rates applicable to the specific situation. This labor table is used in the labor cost portion of this module. It consists of a sequentially numbered list of crews with descriptions, the number of persons in the crew, and their average wage rates.

 

The rates are bare (i.e. without added burden such as payroll taxes or benefits). If the estimator has already defined crews for the company, these crews should replace the default crews. If cost data from a commercial source such as R.S. Means or Dodge Reports are used, the crews on which those data are based must be used. Crews can be added to the labor table as they are needed.

 

Importing a WBS

 

After preparing the crew table for the current estimate, the work breakdown structure created in, the previous module is imported into the WORKPACK module. This (as with almost all operations) is accomplished by choosing an option on a menu.

 

The WBS is placed in the appropriate columns in the direct cost data base. As each new work package is defined, the program calls up the cost code, description, and unit of measure for the next WBI.

 

Development of the work package

 

The information is then entered into the work package report (Figure 1). While some of these data pertain to the project as a whole and will not change for each work package, most of it will be saved to disk and cleared from the entry form so the next work package report can be defined.

 

Figure 1 Workpackage

 

Entering and saving this work package data is done under macro control. This makes the process go very quickly and is almost fool-proof.

 

Labor productivity data is entered as manhours per unit and is immediately displayed as duration, daily production, total manhours, total cost, and cost per unit. This allows the estimator who uses historical data kept as manhours per unit to check the reasonableness of his data. The estimator who does not have access to historical data in this form can enter different manhour per unit values until, by trial and error, he gets the production figures that he wants.

 

Up to 15 different material items can be included in the work package. The units can be mixed and are not related to the quantity on which level of effort is based. A column is devoted to the "source page". This should be used to show where the material quantities come from, i.e., a page number from the take-off.

 

The unit cost for equipment is usually a rental rate and the unit is a unit of time. Only equip­ment that can be directly, charged to this work package should be included at this point. Equip­ment that is used throughout the job can be included in the indirect costs section of the SUMMARY module.

 

Miscellaneous costs are the next to be added. This category is for costs that are directly attributable to this work package but upon which no material or labor taxes will be accessed. Examples that fit this category are minor subcon­tracts that will not be competitively bid or charges such as dump fees.

 

Notes can now be added to better explain and describe the work package. Actually, notes can be added at any time either by hand or with the program. Because this system produces such neat printed output, most users are reluctant to write on the reports. It should be stressed that these documents are for internal use and the better all parts of the estimate are documented the more useful it is.

 

Save work package and update data base

 

After entering the needed data and notes into the work package, the report is printed and then saved to disk through a menu option. At the same time, the "bottom line" data are copied to the summary data base that is part of the WORKPACK module. These data are summarized as each work package is added, giving a running total of the costs and manhours accumulated.

 

Subsequent work packages

 

The preceding procedure is repeated until all of the work breakdown items have been fleshed out with the detailed information that turns them into work packages. At any time, the estimator can print the data base as a report on his progress to date.

 

Each work package uses about 24 kilobytes of disk space. This means that there is only enough room on a 360k disk for about 15 work packages. This can be a problem especially if floppy disks are used. A data compression utility such as SQ. by Turner Hall Publishing, which claims to reduce the amount of disk space needed by Lotus spreadsheets by 80% to 95%, could do much to alleviate this predicament.

 

Save data base

 

The last operation necessary in the WORKPACK module is the exportation of the completed direct cost data base for use in SUMMARY and ANALYSIS modules.

 

Indirect Costs, Subcontracts & Markup (SUMMARY)

 

The third module in the CONEST system adds to the bid all those costs that are not part of the direct costs associated with the work to be done by the estimating contractor. These items include job indirect costs, subcontracts, taxes--both material and labor, insurance, bonds, home office overhead, and profits.

 

The SUMMARY module produces three reports: Job Indirects, Sub Tally, and Markup. Information is automatically transferred from the indirect and subcontract reports to the markup sheet. Direct costs are imported into the markup report through a menu option. The markup sheet is then used as a recap sheet to summarize the bid as a whole.

 

Job indirect costs

 

Expected costs that can be associated with the job but can not be isolated in any one work package, are recorded in the Indirect Cost Report. This section of the module works as a classic spread sheet. The estimator enters a description, quantity and unit, and then the cost per unit of labor, materials, equipment, or miscellaneous for each item. The miscellaneous category is to be used for any costs, other than for equipment, on which the contractor pays no sales tax or labor burden (Figure 2).

 

Figure 2 Indirect Costs.

 

Once this report is completed, it can be saved to use as a starting point on a subsequent similar job. Conversely, if a suitable indirect cost report has already been created and saved, it can be imported into the SUMMARY module and modified to suit the current project.

 

Sub-Tally sheet

 

As bids for portions of the job are received, they are entered into the Sub Tally sheet. The low responsible bids are tagged and only these bids are used in calculating the prices for the prime bid.

 

The general contractor may want to include his own estimates for each of these items to be sublet. This serves three purposes: as a ballpark figure to predict a bid price before all the subs are in; as an indication of the reasonableness of the subcontractor's offers; and as a figure to be used in the event that no reasonable bid is made on an item of work.

 

One of the last operations before the prime bid is made is to verify that the best price for each item to. be subcontracted is tagged. Even changes that are made in the last seconds are reflected in the general contractor's markup of the item (Figure 3).

 

Figure 3 Subcontract Tally Sheet.

 

Markup of the costs

 

The final report in the SUMMARY module is the Markup Report. This serves as a top sheet to summarize the prime bid as well as a place to add costs that are dependent on the items identified so far.

 

Direct costs are imported from either the WORKPACK or ANALYSIS modules. If there were too many work packages to fit into the ANALYSIS module at one time (100 maximum at 256k), this is the point where these costs can be consolidated.

 

The latest indirect and subcontract costs are automatically transferred from the other sections of this module. Provisions have been made to adjust these predicted costs at this time. Specific dollar amounts can be added or subtracted from any category. Adjustments can also be made as a percentage to be added to or removed from the sub total before markup.

 

In addition to consolidation, this top sheet provides a way to markup the costs with those items that are usually figured as a percentage of job cost. Except for profit, these percentages usually remain the same from job to job. See figure 4 for an example of this markup report.

Figure 4 Markup Report

 

Labor burden can be added as a percentage of labor cost and/or in terms of dollars per expected manhour. This is helpful because some burden such as social security is dependent on labor dollars and some items such as fringe benefits, may be calculated on manhours worked [3].

 

Material taxes are computed as a percentage of the predicted material costs. In states where a sales tax is assessed on items other than materials, this rate must be included in the appropriate places.

 

Performance and payment bonds are calculated as a stepped percentage of job cost. The markup sheet includes a small table into which the estimator inserts the steps and rates used by his bonding company. No provision has been made for bid bonds as this item is of negligible cost and, if not paid for as a service by the bonding company, can be included in home office overhead.

 

At the bottom left of the markup sheet are some ratios that aid the executive in determining the amount of profit to put into the bid. These include the ratio of total profit to the contrac­tor's own labor costs, the ratio of subcontracted work to that to be done by the general contractor, and the proportions of labor, material and equipment in the general's work. These ratios are intended to give an indication of the relative riskiness of the project as well as the makeup of the job.

 

Profit is entered in three parts: as a percentage applied to the contractor's own labor and equip­ment costs, as a percentage applied to material to be purchased, and as a percentage of the subcon­tracted work. The program calculates the total profit as both a dollar amount and as a percentage of these figures.

 

 

ANALYSIS

 

After creating the work packages that describe the direct costs associated with the job, the data

base that summarizes those costs can be analyzed using the ANALYSIS module. Use of this module is optional. A bid can be prepared using only WBS, WORKPACK, and SUMMARY.

 

The estimating instructor can take the direct cost data from each of his or her students and compare them in all sorts of ways. This allows for evaluation by exception. The erroneous data will bubble up to the top and can be tagged for further scrutiny.

 

The first step is to import the direct cost summary to be analyzed. If the detailed data have been developed by several different people on different computers, this is a point where it can be consolidated.

 

The ANALYSIS module produces three reports: a sorted direct cost summary, an extracted data report, and a summary by cost code 1 (usually the UCI Division). This module also creates several graphs that show relationships between the work packages and categories of costs.

 

Sorted direct costs

 

The first use of this analysis is in checking the estimate for gross errors. The data can be sorted by any of 13 fields: Project (student), Work package, Cost code 1, Cost code 2, Description, Unit of measure, Manhours, Labor cost, Equipment cost, Material cost, Miscellaneous cost, Total cost, and Cost per unit.

 

Sorting the work packages by the appropriate fields helps to determine whether any of the costs are out of proportion. The sorted reports can be printed under menu control at any time.

 

It is often beneficial, to sort by total cost to see which work packages are most critical to the price of the job as a whole. This sort will indicate work packages that might be too insignif­icant to be separately considered. If this is the case, the WORKPACK module can combine these insignificant items into other work packages.

 

A sort by manhours budgeted will give an indication of the items that require the most management attention. This is significant because although there is not much that can be done about expensive materials, there is a lot that can be done that affects labor productivity.

 

This sorted data report also has a field containing the total cost of each work package as a cost per unit of the controlling unit of measure. It is not often useful to sort by this field, but it can be very productive to check these unit costs against the company's and/or industry historical data.

 

Graphs

 

The sorted data base can also be viewed graphically. There are two predefined graphs: the first shows the proportion of labor, equipment and materials to the total direct costs (excluding subcontracts); the second shows the relative total cost of the first forty work packages in the sorted list (see the example in Figure 5 below).

 

Figure 5 A Sample Graph.

 

Data extraction

 

The second major part of the ANALYSIS module is called "Data-Query" on the menu. This section produces a report based on information extracted from the direct cost data base. Criteria are entered under headings that duplicate the field names in the data base. Any work packages that meet these criteria are then listed in the DataQuery report and the totals are calculated.

 

By entering complex criteria such as -- CC1=3 or CC1=5 and Manhours > 1000 or Total cost > 10000 -- the estimator can list very specific data.. In the above example, he would get a list of all the work packages in Division 3 (concrete) or Division 5 (metals) that were estimated to take over 1000 manhours to complete or were expected to cost more than $10,000.

 

Summary by CC1 (UCI Division)

 

The third and last major section of ANALYSIS is a predefined direct cost summary report. In the default configuration, this report is set up to summarize the direct costs by cost code 1 which the author suggests contain the UCI Division. This report can be modified to summarize data by either of the cost codes or a combination of both.

 

In this default configuration, the report shows the total Manhours, Labor, Material, Equipment, Miscellaneous, and Total Costs for each of the 16 UCI Divisions.            See the example in Figure 6.

 

Figure 6 Summary by Division.

 

 

USING CONEST IN AN ESTIMATING CLASS

 

Using CONEST in a class room situation is a little different than using it in a business. The student usually only gets to prepare one estimate and does not have a library of work breakdown structures or work packages to work with. As with most computer programs much of the benefit comes with repetition. It should be pointed out that because this is the first time they are using the system some of their time will be spent setting up the structure and learning the system.

 

Once a work breakdown structure and labor table have been created it takes an average of about five minutes per work package to complete an estimate. This comes. from the author's observa­tions of about thirty students who were using the system for the first time.

 

Suggestions

 

I have had the best results when students, after being given a detailed introduction to the work breakdown structure and work package concepts, developed a preliminary WBS and crew table before they did a quantity takeoff. This way they organized the takeoff data in a structure that was compatible with their WBS and labor resources. During the takeoff process modifications will be made to both the WBS and the crew table. These modifications are easy to implement with the system once the students get back on the computers.

 

The instructor will want the students to turn in a fully documented hard copy of all the estimate documents as well as a disk file with their direct cost database. The instructor can then combine these databases and use the ANALYSIS module to find the $42 per .S.F. welded wire mesh and the $1 per C.Y. hand excavation.

 

If the class and/or the estimates are large and the instructor does not have enough RAM to analyze the data all at once, I suggest that the students be required to turn in their direct cost databases in two or three files separated by CSI Division. The instructor could then combine like Divisions and work with these smaller files.

 

 

CONCLUSION

 

CONEST is an inexpensive (about the same price as a textbook) construction pricing and bidding system. It is a medium conducive to teaching good estimating practices as well as computer skills. Like most good computer software it not only saves time but aids in the production of a superior product. In this case the superior product is not only the estimate and bid but the instructor's evaluation of those documents.

 

 

REFERENCES

 

1. Tiner, W. Douglas and Buckingham, Winfred L., Construction Planning, (Texas A&M University, College Station, Texas, Unpublished, 1982), pp. 8.

 

2. Tiner, W. Douglas, "Subdivision of work on construction       projects", Project Management, February 1985, (Butterworth & Co. Ltd., 1985). pp. 13-18.

 

3.Clough, Richard H., Construction Contracting, (New York: John Wiley and Sons, 1975), pp. 64-111.